A63 Roger Millward Way roundabout improvements

Theresa Morley

Works to put new traffic signals on the roundabout and build two new lanes through the middle of the roundabout. The new ‘hamburger’ style layout will mean that traffic can pass through the roundabout when travelling east or west.

The works will also involve building extra lanes on the roundabout exits as well as creating a new lane, within the existing road, on the eastbound approach.

Work will start on 5 November and there will be road closures for five nights from 5 November to 9 November. To minimise disruption to customers, work will take place overnight when there are fewer vehicles on the road.

After this, we’ll be working 7 days a week to complete all work on roundabout work as quickly as possible.