M62 junction 10 to 12 smart motorway

We're improving the 9.8-mile section of the M62 between junctions 10 and 12 by upgrading it to an all-lane running smart motorway.

Region:  North West
Start date:  2017-18
Cost:  ¬£100 million - ¬£250 million
Status:  CURRENT
Type:  Major Scheme
End date:  2019-20
Programme:  North-west smart motorways

Progress report

Temporary narrow lanes are in operation on the nine-mile stretch of the M62 between junctions 10 and 12.

Since January 2019 we've removed six overhead gantries and have installed more than a mile of concrete barrier in the central reservation. We're now using a contraflow system to manage flow of traffic during main construction work (including gantry installations). This means drivers may be travelling in a narrower lane than normal and with a temporary barrier between them and oncoming traffic.

In order to operate these narrow lanes, some lane restrictions are needed on the slip roads from junctions 10, 11 and 12. This is so we can safely filter traffic into and out of these narrow lanes and to ensure we complete the scheme by spring 2020.

On the M62 itself, a minimum of three lanes will be maintained in both directions during construction.

In the meantime, major road improvement works in and around Regent Road are continuing. The Manchester and Salford Inner Relief Route improvement scheme is being delivered by Manchester and Salford City Councils.

You can find out more about progress and next steps in our summer 2019 newsletter.

What's next?

One of the exit lanes from the eastbound M62 onto the clockwise M60 at junction 12 will need to be temporarily closed from Tuesday 4 June until September so that contractors can work safely at the edge of the road.

The road layout will be changed so that drivers can continue to use two lanes to reach the clockwise M60.

Drivers are being advised to allow extra time for their journeys while they get used to the new road layout, and to consider using alternative routes such as the M61 for vehicles travelling from the north of the region and the A556 and M56 from the south.

We expect the full smart motorway scheme to be completed by spring 2020.

Timeline

Date Event
December 2014 Government announces scheme
Summer 2018 Works start
Spring 2020 Works complete

Why we need this scheme

The M62 motorway is a strategic route for local, regional and international traffic and plays a major role as a cross-country artery between the north-west, Yorkshire and Humberside. This section of the M62 carries in excess of 110,000 vehicles per day.

The M62 carries high volumes of heavy goods and other vehicles. Congestion and unreliable journey times are currently experienced at busy periods and traffic is predicted to grow.

The M62 project will relieve congestion and smooth the flow of traffic, improving journey times as well as improving the current unpredictability of journey times along this stretch of the motorway.

Aims

With this scheme, we aim to:

  • reduce congestion and smooth the flow of traffic to improve travel times, making journeys more reliable
  • support the economy and facilitate economic growth within the region. Providing much-needed capacity on the motorway will reduce the cost of delays to both commuters and business traffic
  • continue to deliver a high level of safety performance on the network using smart motorway techniques
  • minimise environmental impacts

The scheme in detail

The M62 between junctions 10 and 12 is a key strategic route carrying high volumes of vehicles between Liverpool and Manchester. The scheme falls within the Area 10 maintenance area and the North West Regional Control Centre.

Smart motorways are a technology driven approach to tackling the most congested parts of the motorway network, improving journey reliability by controlling the flow and speed of traffic. They also support the economy by providing much-needed capacity on the busiest motorways, while maintaining safety for road users and those who work on the roads.

The design features of the scheme include:

  • variable mandatory speed limits
  • driver information, including lane availability, provided through a mixture of gantries and cantilever signs
  • queue detection and automatic signalling system, which provides queue protection and congestion management
  • comprehensive low light pan-tilt-zoom CCTV coverage
  • refuge areas where drivers can stop in an emergency

Environmental impact

We're undertaking an environmental assessment that covers topics including noise and vibration, water, air quality, ecology and visual impacts. The results will be presented in an Environmental Assessment Report where we'll describe the measures we'll take to minimise potentially significant adverse environmental effects.

Project media files and documents

There are no images for this project
There are no videos for this project

Project timeline

Planned roadworks

Roadworks and Events for England

The latest incident information for England's motorway and trunk routes provided by Highways England

Location : The M62 westbound between junctions J12 and J11 . Lane Closures : Lane three is closed. Reason : Roadworks. Status : Currently Active. Period : expect disruption until 06:00 on 31 March 2020. Lanes Closed : There is one of four lanes closed.
Posted: October 16, 2019, 1:49 pm
Location : The M60 clockwise between junctions J15 and J18 . Lane Closures : The hard shoulder is closed. Reason : Roadworks. Status : Currently Active. Period : expect disruption until 17:00 on 30 November 2019.
Posted: October 16, 2019, 1:01 pm
Location : The M602 westbound between junctions J2 and J1 . Lane Closures : Lane three is closed. Reason : Roadworks. Status : Currently Active. Period : expect disruption until 06:00 on 31 March 2020. Lanes Closed : There is one of four lanes closed.
Posted: October 16, 2019, 12:56 pm
Location : The M60 clockwise between junctions J6 and J12 . Lane Closures : The hard shoulder is closed. Reason : Roadworks. Status : Currently Active. Period : expect disruption until 17:00 on 30 November 2019.
Posted: October 16, 2019, 12:50 pm
Location : The M60 clockwise between junctions J12 and J15 . Lane Closures : The hard shoulder is closed. Reason : Roadworks. Status : Currently Active. Period : expect disruption until 17:00 on 30 November 2019.
Posted: October 16, 2019, 12:18 pm
Location : The M56 westbound entry slip at junction J8 . Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : From 21:00 on 16 October 2019 to 05:00 on 17 October 2019. Schedule : From 21:00 on 18 October 2019 to 05:00 on 19 October 2019. Lanes Closed : All lanes will be closed.
Posted: October 16, 2019, 12:15 pm
Location : The M56 westbound exit slip at junction J9 to A50. Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 05:00 from 17 October 2019 to 19 October 2019. Lanes Closed : All lanes will be closed.
Posted: October 16, 2019, 12:15 pm
Location : The M56 westbound between junctions J8 and J9 to A50. Reason : Roadworks scheme is planned. Status : Pending. Schedule : From 21:00 on 16 October 2019 to 05:00 on 19 October 2019.
Posted: October 16, 2019, 12:15 pm
Location : The M6 northbound entry slip at junction J20 from the M56 west. Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 05:00 from 17 October 2019 to 19 October 2019. Lanes Closed : All lanes will be closed.
Posted: October 16, 2019, 12:15 pm
Location : The M6 southbound entry slip at junction J21A from M62 Westbound. Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 06:00 from 16 October 2019 to 20 October 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 22 October 2019 to 26 October 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 28 October 2019 to 2 November 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 12 November 2019 to 17 November 2019. Lanes Closed : All lanes will be closed.
Posted: October 16, 2019, 12:14 pm
Location : The M6 northbound entry slip at junction J21A from M62 westbound. Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 06:00 from 16 October 2019 to 20 October 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 22 October 2019 to 26 October 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 28 October 2019 to 2 November 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 12 November 2019 to 17 November 2019. Lanes Closed : All lanes will be closed.
Posted: October 16, 2019, 12:14 pm
Location : The M62 westbound exit slip at junction J10 . Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 06:00 from 16 October 2019 to 20 October 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 22 October 2019 to 26 October 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 28 October 2019 to 2 November 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 12 November 2019 to 17 November 2019. Lanes Closed : All lanes will be closed.
Posted: October 16, 2019, 12:14 pm
Location : The M602 westbound at junction J1 . Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : From 21:00 on 21 October 2019 to 06:00 on 22 October 2019. Schedule : From 21:00 on 26 October 2019 to 06:00 on 27 October 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 28 October 2019 to 31 October 2019. Schedule : From 21:00 on 1 November 2019 to 06:00 on 2 November 2019. Lanes Closed : All lanes will be closed.
Posted: October 16, 2019, 12:07 pm
Location : The M6 northbound entry slip at junction J21A from M62 westbound. Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : From 21:00 on 21 October 2019 to 06:00 on 22 October 2019. Schedule : From 21:00 on 26 October 2019 to 06:00 on 27 October 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 28 October 2019 to 31 October 2019. Schedule : From 21:00 on 1 November 2019 to 06:00 on 2 November 2019. Lanes Closed : All lanes will be closed.
Posted: October 16, 2019, 12:07 pm
Location : The M60 anticlockwise exit slip at junction J12 . Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : From 21:00 on 21 October 2019 to 06:00 on 22 October 2019. Schedule : From 21:00 on 26 October 2019 to 06:00 on 27 October 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 28 October 2019 to 31 October 2019. Schedule : From 21:00 on 1 November 2019 to 06:00 on 2 November 2019. Lanes Closed : All lanes will be closed.
Posted: October 16, 2019, 12:07 pm
Location : The M6 southbound entry slip at junction J21A from M62 Westbound. Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : From 21:00 on 21 October 2019 to 06:00 on 22 October 2019. Schedule : From 21:00 on 26 October 2019 to 06:00 on 27 October 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 28 October 2019 to 31 October 2019. Schedule : From 21:00 on 1 November 2019 to 06:00 on 2 November 2019. Lanes Closed : All lanes will be closed.
Posted: October 16, 2019, 12:07 pm
Location : The M60 clockwise between junctions J11 and J12 . Lane Closures : Lane one will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : From 21:00 on 21 October 2019 to 06:00 on 22 October 2019. Schedule : From 21:00 on 26 October 2019 to 06:00 on 27 October 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 28 October 2019 to 31 October 2019. Schedule : From 21:00 on 1 November 2019 to 06:00 on 2 November 2019. Lanes Closed : There will be one of three lanes closed.
Posted: October 16, 2019, 12:07 pm
Location : The M60 anticlockwise between junctions J13 and J12 . Lane Closures : Lane one will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : From 21:00 on 21 October 2019 to 06:00 on 22 October 2019. Schedule : From 21:00 on 26 October 2019 to 06:00 on 27 October 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 28 October 2019 to 31 October 2019. Schedule : From 21:00 on 1 November 2019 to 06:00 on 2 November 2019. Lanes Closed : There will be one of four lanes closed.
Posted: October 16, 2019, 12:07 pm
Location : The M60 anticlockwise at junction J12 . Lane Closures : Lane one will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : From 21:00 on 21 October 2019 to 06:00 on 22 October 2019. Schedule : From 21:00 on 26 October 2019 to 06:00 on 27 October 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 28 October 2019 to 31 October 2019. Schedule : From 21:00 on 1 November 2019 to 06:00 on 2 November 2019. Lanes Closed : There will be one of two lanes closed.
Posted: October 16, 2019, 12:07 pm
Location : The M62 westbound between junctions J12 and J10 . Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : From 21:00 on 21 October 2019 to 06:00 on 22 October 2019. Schedule : From 21:00 on 26 October 2019 to 06:00 on 27 October 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 28 October 2019 to 31 October 2019. Schedule : From 21:00 on 1 November 2019 to 06:00 on 2 November 2019. Lanes Closed : All lanes will be closed.
Posted: October 16, 2019, 12:07 pm
Location : The M62 westbound exit slip at junction J11 . Reason : Roadworks are planned. Status : Pending. Schedule : From 21:00 on 21 October 2019 to 06:00 on 22 October 2019. Schedule : From 21:00 on 26 October 2019 to 06:00 on 27 October 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 28 October 2019 to 31 October 2019. Schedule : From 21:00 on 1 November 2019 to 06:00 on 2 November 2019. Lanes Closed : All lanes will be closed.
Posted: October 16, 2019, 12:07 pm
Location : The M62 westbound entry slip at junction J11 . Reason : Roadworks are planned. Status : Pending. Schedule : From 21:00 on 21 October 2019 to 06:00 on 22 October 2019. Schedule : From 21:00 on 26 October 2019 to 06:00 on 27 October 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 28 October 2019 to 31 October 2019. Schedule : From 21:00 on 1 November 2019 to 06:00 on 2 November 2019. Lanes Closed : All lanes will be closed.
Posted: October 16, 2019, 12:07 pm
Location : The M62 westbound exit slip at junction J10 . Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : From 21:00 on 21 October 2019 to 06:00 on 22 October 2019. Schedule : From 21:00 on 26 October 2019 to 06:00 on 27 October 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 28 October 2019 to 31 October 2019. Schedule : From 21:00 on 1 November 2019 to 06:00 on 2 November 2019. Lanes Closed : All lanes will be closed.
Posted: October 16, 2019, 12:07 pm
Location : The M62 westbound entry slip at junction J12 . Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : From 21:00 on 21 October 2019 to 06:00 on 22 October 2019. Schedule : From 21:00 on 26 October 2019 to 06:00 on 27 October 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 28 October 2019 to 31 October 2019. Schedule : From 21:00 on 1 November 2019 to 06:00 on 2 November 2019. Lanes Closed : All lanes will be closed.
Posted: October 16, 2019, 12:07 pm
Location : The M60 clockwise at junction J4 . Lane Closures : The hard shoulder is closed. Reason : Roadworks. Status : Currently Active. Period : expect disruption until 17:00 on 30 November 2019.
Posted: October 16, 2019, 12:06 pm
Location : The M60 clockwise between junctions J4 and J6 . Lane Closures : The hard shoulder is closed. Reason : Roadworks. Status : Currently Active. Period : expect disruption until 17:00 on 30 November 2019.
Posted: October 16, 2019, 12:06 pm
Location : The M60 clockwise between junctions J1 and J3 . Lane Closures : The hard shoulder is closed. Reason : Roadworks. Status : Currently Active. Period : expect disruption until 17:00 on 30 November 2019.
Posted: October 16, 2019, 12:06 pm
Location : The M60 clockwise between junctions J24 and J2 . Lane Closures : The hard shoulder is closed. Reason : Roadworks. Status : Currently Active. Period : expect disruption until 17:00 on 30 November 2019.
Posted: October 16, 2019, 12:06 pm
Location : The M60 clockwise at junction J6 . Lane Closures : The hard shoulder is closed. Reason : Roadworks. Status : Currently Active. Period : expect disruption until 17:00 on 30 November 2019.
Posted: October 16, 2019, 12:06 pm
Location : The M60 clockwise at junction J15 after J14 access. Lane Closures : The hard shoulder is closed. Reason : Roadworks. Status : Currently Active. Period : expect disruption until 17:00 on 30 November 2019.
Posted: October 16, 2019, 12:06 pm
Location : The M60 clockwise between junctions J5 and J6 . Lane Closures : The hard shoulder is closed. Reason : Barrier repairs. Status : Currently Active. Period : expect disruption until 23:59 on 31 December 2019.
Posted: October 16, 2019, 9:04 am
Location : The M6 southbound between junctions J22 and J21A . Reason : Roadworks scheme. Status : Currently Active. Period : from 21:00 on 14 October 2019 to 06:00 on 15 December 2019.
Posted: October 16, 2019, 8:54 am
Location : The M60 anticlockwise exit slip at junction J2 . Lane Closures : Lane one is closed. Reason : Road repairs. Status : Currently Active. Period : expect disruption until 15:30 on 16 October 2019. Lanes Closed : There is one of two lanes closed.
Posted: October 16, 2019, 8:31 am
Location : The M61 southbound between junctions A666 and J2 from A666 to M60. Lane Closures : The hard shoulder is closed. Reason : Emergency barrier repairs. Status : Currently Active. Period : expect disruption until 23:59 on 31 December 2019.
Posted: October 16, 2019, 8:01 am
Location : The M6 southbound between junctions J21A and J21 . Lane Closures : The hard shoulder is closed. Reason : Roadworks. Status : Currently Active. Period : expect disruption until 06:00 on 31 December 2021.
Posted: October 16, 2019, 8:01 am
Location : The M61 southbound between junctions A666 and J2 . Lane Closures : The hard shoulder is closed. Reason : Emergency roadworks. Status : Currently Active. Period : expect disruption until 06:00 on 31 December 2019.
Posted: October 16, 2019, 8:01 am
Location : The M6 northbound between junctions J23 and J26 . Lane Closures : The hard shoulder is closed. Reason : Barrier repairs. Status : Currently Active. Period : expect disruption until 23:59 on 31 December 2019.
Posted: October 16, 2019, 7:50 am
Location : The M6 southbound between junctions J20A and J19 . Lane Closures : The hard shoulder is closed. Reason : Roadworks. Status : Currently Active. Period : expect disruption until 00:00 on 8 November 2019.
Posted: October 16, 2019, 7:32 am
Location : The M56 westbound between junctions J3A and J3 . Lane Closures : The hard shoulder is closed. Reason : Emergency roadworks. Status : Currently Active. Period : expect disruption until 05:00 on 30 November 2019.
Posted: October 16, 2019, 7:31 am
Location : The M62 eastbound between junctions J9 and J12 . Reason : Roadworks scheme. Status : Currently Active. Period : from 21:00 on 14 October 2019 to 06:00 on 15 December 2019.
Posted: October 16, 2019, 6:37 am
Location : The M6 northbound at junction J21A . Lane Closures : Lane one will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 06:00 from 16 October 2019 to 20 October 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 28 October 2019 to 17 November 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 18 November 2019 to 28 November 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 9 December 2019 to 15 December 2019. Lanes Closed : There will be one of four lanes closed.
Posted: October 16, 2019, 5:03 am
Location : The M602 eastbound at junction J1 . Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 06:00 from 16 October 2019 to 20 October 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 28 October 2019 to 17 November 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 18 November 2019 to 28 November 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 9 December 2019 to 15 December 2019. Lanes Closed : All lanes will be closed.
Posted: October 16, 2019, 5:03 am
Location : The M6 northbound at junction J21A . Lane Closures : Lane one will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 06:00 from 16 October 2019 to 20 October 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 28 October 2019 to 17 November 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 18 November 2019 to 28 November 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 9 December 2019 to 15 December 2019. Lanes Closed : There will be one of three lanes closed.
Posted: October 16, 2019, 5:03 am
Location : The M62 eastbound between junctions J9 and J12 . Lane Closures : Lane one will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 06:00 from 16 October 2019 to 20 October 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 28 October 2019 to 17 November 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 18 November 2019 to 28 November 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 9 December 2019 to 15 December 2019. Lanes Closed : All lanes will be closed.
Posted: October 16, 2019, 5:03 am
Location : The M62 eastbound exit slip at junction J11 . Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 06:00 from 16 October 2019 to 20 October 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 28 October 2019 to 17 November 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 18 November 2019 to 28 November 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 9 December 2019 to 15 December 2019. Lanes Closed : All lanes will be closed.
Posted: October 16, 2019, 5:03 am
Location : The M6 southbound between junctions J22 and J21A . Lane Closures : Lane one will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 06:00 from 16 October 2019 to 20 October 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 28 October 2019 to 17 November 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 18 November 2019 to 28 November 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 9 December 2019 to 15 December 2019. Lanes Closed : There will be one of three lanes closed.
Posted: October 16, 2019, 5:03 am
Location : The M60 clockwise entry slip at junction J12 from M62 Eastbound. Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 06:00 from 16 October 2019 to 20 October 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 28 October 2019 to 17 November 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 18 November 2019 to 28 November 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 9 December 2019 to 15 December 2019. Lanes Closed : All lanes will be closed.
Posted: October 16, 2019, 5:02 am
Location : The M60 anticlockwise entry slip at junction J12 . Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 06:00 from 16 October 2019 to 20 October 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 28 October 2019 to 17 November 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 18 November 2019 to 28 November 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 9 December 2019 to 15 December 2019. Lanes Closed : All lanes will be closed.
Posted: October 16, 2019, 5:02 am
Location : The M6 southbound exit slip at junction J21A to M62 East. Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 06:00 from 15 October 2019 to 20 October 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 28 October 2019 to 17 November 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 18 November 2019 to 28 November 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 9 December 2019 to 15 December 2019. Lanes Closed : All lanes will be closed.
Posted: October 16, 2019, 4:05 am
Location : The M6 northbound exit slip at junction J21A to M62 east. Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 06:00 from 15 October 2019 to 20 October 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 28 October 2019 to 17 November 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 18 November 2019 to 28 November 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 9 December 2019 to 15 December 2019. Lanes Closed : All lanes will be closed.
Posted: October 16, 2019, 3:55 am
Location : The M62 eastbound entry slip at junction J11 . Lane Closures : Lane one will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 06:00 from 15 October 2019 to 20 October 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 28 October 2019 to 17 November 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 18 November 2019 to 28 November 2019. Schedule : Expect disruption everyday between 21:00 and 06:00 from 9 December 2019 to 15 December 2019. Lanes Closed : All lanes will be closed.
Posted: October 16, 2019, 3:51 am
Location : The M6 southbound between junctions J26 and J23 . Lane Closures : Lanes 2 and 3 will be closed. Reason : Roadside drains works are planned. Status : Pending. Schedule : From 21:00 on 22 October 2019 to 05:00 on 23 October 2019. Lanes Closed : There will be two of three lanes closed.
Posted: October 15, 2019, 8:14 pm
Location : The M60 clockwise between junctions J13 and J15 . Lane Closures : The hard shoulder is closed. Reason : Barrier repairs. Status : Currently Active. Period : expect disruption until 23:59 on 31 December 2019.
Posted: October 15, 2019, 4:20 pm
Location : The M602 eastbound between junctions J1 and J2 . Lane Closures : The hard shoulder is closed. Reason : Barrier repairs. Status : Currently Active. Period : expect disruption until 23:59 on 31 December 2019.
Posted: October 15, 2019, 4:20 pm
Location : The M602 westbound at junction J1 . Reason : Roadworks. Status : Currently Active. Period : expect disruption until 06:00 on 31 March 2020.
Posted: October 15, 2019, 4:20 pm
Location : The M6 northbound exit slip at junction J19 . Lane Closures : Lane one will be closed. Reason : Litter clearance is planned. Status : Pending. Schedule : Expect disruption everyday between 21:30 and 05:00 from 21 October 2019 to 24 October 2019. Lanes Closed : There will be one of two lanes closed.
Posted: October 15, 2019, 4:20 pm
Location : The M602 eastbound at junction J1 . Lane Closures : The hard shoulder is closed. Reason : Barrier repairs. Status : Currently Active. Period : expect disruption until 23:59 on 31 December 2019.
Posted: October 15, 2019, 4:20 pm
Location : The M60 clockwise entry slip at junction J5 . Lane Closures : The hard shoulder is closed. Reason : Barrier repairs. Status : Currently Active. Period : expect disruption until 23:59 on 31 December 2019.
Posted: October 15, 2019, 4:20 pm
Location : The M56 westbound entry slip at junction J10 . Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 06:00 from 21 October 2019 to 23 October 2019. Lanes Closed : All lanes will be closed.
Posted: October 15, 2019, 4:20 pm
Location : The M60 anticlockwise at junction J4 . Lane Closures : The hard shoulder is closed. Reason : Barrier repairs. Status : Currently Active. Period : expect disruption until 05:30 on 31 December 2019.
Posted: October 15, 2019, 4:20 pm
Location : The M60 anticlockwise between junctions J8 and J6 through lane. Lane Closures : The hard shoulder is closed. Reason : Barrier repairs. Status : Currently Active. Period : expect disruption until 23:59 on 31 December 2019.
Posted: October 15, 2019, 4:20 pm
Location : The M60 anticlockwise between junctions J5 and J4 . Lane Closures : The hard shoulder is closed. Reason : Barrier repairs. Status : Currently Active. Period : expect disruption until 23:59 on 31 December 2019.
Posted: October 15, 2019, 4:20 pm
Location : The M60 anticlockwise between junctions J5 and J4 . Lane Closures : The hard shoulder is closed. Reason : Barrier repairs. Status : Currently Active. Period : expect disruption until 05:30 on 31 December 2019.
Posted: October 15, 2019, 4:20 pm
Location : The M60 clockwise between junctions J4 and J5 . Lane Closures : The hard shoulder is closed. Reason : Barrier repairs. Status : Currently Active. Period : expect disruption until 23:59 on 31 December 2019.
Posted: October 15, 2019, 4:20 pm
Location : The A5103 northbound between the junctions with the M56 and the M60 . Lane Closures : Lane three will be closed. Reason : Barrier repairs are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 05:00 from 16 October 2019 to 19 October 2019. Lanes Closed : There will be one of four lanes closed.
Posted: October 15, 2019, 4:20 pm
Location : The M60 clockwise entry slip at junction J14 . Lane Closures : Lane two is closed. Reason : Roadworks. Status : Currently Active. Period : expect disruption until 06:00 on 31 January 2020. Lanes Closed : There is one of two lanes closed.
Posted: October 15, 2019, 4:20 pm
Location : The M61 northbound exit slip at junction J6 . Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : From 20:00 on 21 October 2019 to 05:00 on 22 October 2019. Schedule : Expect disruption everyday between 20:00 and 05:00 from 23 October 2019 to 25 October 2019. Schedule : From 20:00 on 25 October 2019 to 07:00 on 26 October 2019. Schedule : From 20:00 on 26 October 2019 to 10:00 on 27 October 2019. Lanes Closed : All lanes will be closed.
Posted: October 15, 2019, 4:20 pm
Location : The M6 northbound between junctions J21 and J21A . Lane Closures : The hard shoulder is closed. Reason : Roadworks. Status : Currently Active. Period : expect disruption until 06:00 on 31 December 2021.
Posted: October 15, 2019, 4:20 pm
Location : The M6 southbound between junctions J27 and J21 . Reason : Roadworks scheme. Status : Currently Active. Period : from 14:52 on 21 January 2019 to 06:00 on 31 December 2021.
Posted: October 15, 2019, 4:20 pm
Location : The M6 southbound between junctions J27 and J21A . Lane Closures : The hard shoulder is closed. Reason : Roadworks. Status : Currently Active. Period : expect disruption until 06:00 on 31 December 2021.
Posted: October 15, 2019, 4:20 pm
Location : The M56 eastbound at junction J3A . Lane Closures : Lane three will be closed. Reason : Barrier repairs are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 05:00 from 16 October 2019 to 19 October 2019. Lanes Closed : There will be one of three lanes closed.
Posted: October 15, 2019, 4:20 pm
Location : The A556 southbound between the M56 and the junction with the M6 . Lane Closures : Lane one will be closed. Reason : Litter clearance is planned. Status : Pending. Schedule : Expect disruption everyday between 21:30 and 05:00 from 21 October 2019 to 24 October 2019. Lanes Closed : There will be one of two lanes closed.
Posted: October 15, 2019, 4:20 pm
Location : The M6 northbound entry slip at junction J19 . Lane Closures : Lane one will be closed. Reason : Litter clearance is planned. Status : Pending. Schedule : Expect disruption everyday between 21:30 and 05:00 from 21 October 2019 to 24 October 2019. Lanes Closed : There will be one of two lanes closed.
Posted: October 15, 2019, 4:20 pm
Location : The M6 southbound exit slip at junction J21A to M62 West. Lane Closures : Lane two is closed. Reason : Roadworks. Status : Currently Active. Period : expect disruption until 23:59 on 31 March 2020. Lanes Closed : There is one of two lanes closed.
Posted: October 15, 2019, 4:20 pm
Location : The M6 northbound exit slip at junction J21A to M62 east. Lane Closures : Lane one is closed. Reason : Roadworks. Status : Currently Active. Period : expect disruption until 06:00 on 31 March 2020. Lanes Closed : There is one of two lanes closed.
Posted: October 15, 2019, 4:20 pm
Location : The M61 northbound entry slip at junction J6 . Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 20:00 and 05:00 from 21 October 2019 to 23 October 2019. Schedule : From 20:00 on 24 October 2019 to 05:00 on 25 October 2019. Schedule : From 20:00 on 25 October 2019 to 07:00 on 26 October 2019. Schedule : From 20:00 on 1 November 2019 to 07:00 on 2 November 2019. Lanes Closed : All lanes will be closed.
Posted: October 15, 2019, 4:20 pm
Location : The M602 eastbound between junctions J1 and J2 . Lane Closures : The hard shoulder is closed. Reason : Roadworks. Status : Currently Active. Period : expect disruption until 23:59 on 31 December 2019.
Posted: October 15, 2019, 4:20 pm
Location : The M61 southbound between junctions J4 and J3 . Lane Closures : Lanes 2 and 3 will be closed. Reason : Roadside drains works are planned. Status : Pending. Schedule : From 21:00 on 21 October 2019 to 05:00 on 22 October 2019. Lanes Closed : There will be two of three lanes closed.
Posted: October 15, 2019, 4:20 pm
Location : The M602 westbound between junctions J2 and J1 . Reason : Roadworks scheme. Status : Currently Active. Period : from 22:01 on 13 December 2018 to 06:00 on 31 March 2020.
Posted: October 15, 2019, 4:20 pm
Location : The M61 southbound between junctions and J2 . Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : From 22:00 on 19 October 2019 to 10:00 on 20 October 2019. Lanes Closed : All lanes will be closed.
Posted: October 15, 2019, 4:20 pm
Location : The M56 westbound between junctions J3A and J3 . Lane Closures : Lane three will be closed. Reason : Barrier repairs are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 05:00 from 16 October 2019 to 19 October 2019. Lanes Closed : There will be one of three lanes closed.
Posted: October 15, 2019, 4:20 pm
Location : The M60 clockwise entry slip at junction J14 . Reason : Roadworks scheme. Status : Currently Active. Period : from 12:21 on 5 November 2018 to 06:00 on 31 January 2020.
Posted: October 15, 2019, 4:20 pm
Location : The M6 southbound exit slip at junction J19 . Lane Closures : Lane one will be closed. Reason : Litter clearance is planned. Status : Pending. Schedule : Expect disruption everyday between 21:30 and 05:00 from 21 October 2019 to 24 October 2019. Lanes Closed : There will be one of two lanes closed.
Posted: October 15, 2019, 4:20 pm
Location : The A5103 southbound between the junctions with the M60 and the M56 . Lane Closures : Lane three will be closed. Reason : Barrier repairs are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 05:00 from 16 October 2019 to 19 October 2019. Lanes Closed : There will be one of four lanes closed.
Posted: October 15, 2019, 4:20 pm
Location : The M61 southbound at junction J2 from M61 to A580. Lane Closures : The hard shoulder is closed. Reason : Emergency barrier repairs. Status : Currently Active. Period : expect disruption until 23:59 on 31 December 2019.
Posted: October 15, 2019, 4:20 pm
Location : The M62 eastbound between junctions J8 and J9 . Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 22:00 and 05:00 from 21 October 2019 to 23 October 2019. Schedule : Expect disruption everyday between 22:00 and 05:00 from 29 October 2019 to 31 October 2019. Lanes Closed : There will be two of four lanes closed.
Posted: October 15, 2019, 4:20 pm
Location : The M61 northbound between junction J3 and the A6053 . Lane Closures : Lanes 1, 2 and 3 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : From 22:00 on 19 October 2019 to 10:00 on 20 October 2019. Lanes Closed : All lanes will be closed.
Posted: October 15, 2019, 4:20 pm
Location : The M62 westbound between junctions J12 and J10 . Reason : Roadworks scheme is planned. Status : Pending. Schedule : From 21:00 on 21 October 2019 to 06:00 on 4 January 2020.
Posted: October 15, 2019, 4:20 pm
Location : The M62 eastbound at junction J8 . Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 22:00 and 05:00 from 21 October 2019 to 23 October 2019. Schedule : Expect disruption everyday between 22:00 and 05:00 from 29 October 2019 to 31 October 2019. Lanes Closed : There will be two of three lanes closed.
Posted: October 15, 2019, 4:20 pm
Location : The M62 westbound between junctions J9 and J8 . Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 22:00 and 05:00 from 21 October 2019 to 23 October 2019. Schedule : From 21:00 on 23 October 2019 to 05:00 on 24 October 2019. Lanes Closed : There will be two of four lanes closed.
Posted: October 15, 2019, 4:20 pm
Location : The M61 northbound between junctions J2 and J4 . Lane Closures : Lanes 2 and 3 will be closed. Reason : Roadside drains works are planned. Status : Pending. Schedule : From 22:45 on 21 October 2019 to 05:00 on 22 October 2019. Lanes Closed : There will be two of three lanes closed.
Posted: October 15, 2019, 4:20 pm
Location : The A5103 southbound at the junction with the M60 . Lane Closures : Lane three will be closed. Reason : Barrier repairs are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 05:00 from 16 October 2019 to 19 October 2019. Lanes Closed : There will be one of three lanes closed.
Posted: October 15, 2019, 4:20 pm
Location : The M60 anticlockwise between junctions J13 and J12 . Reason : Roadworks scheme is planned. Status : Pending. Schedule : From 21:00 on 21 October 2019 to 06:00 on 4 January 2020.
Posted: October 15, 2019, 4:20 pm
Location : The M6 northbound exit slip at junction J21A to M62 east. Reason : Roadworks scheme. Status : Currently Active. Period : from 21:00 on 14 October 2019 to 06:00 on 15 December 2019.
Posted: October 15, 2019, 4:20 pm
Location : The A556 northbound between the M6 and the junction with the M56 . Lane Closures : Lane one will be closed. Reason : Litter clearance is planned. Status : Pending. Schedule : Expect disruption everyday between 21:30 and 05:00 from 21 October 2019 to 24 October 2019. Lanes Closed : There will be one of two lanes closed.
Posted: October 15, 2019, 4:20 pm
Location : The M6 southbound entry slip at junction J19 . Lane Closures : Lane one will be closed. Reason : Litter clearance is planned. Status : Pending. Schedule : Expect disruption everyday between 21:30 and 05:00 from 21 October 2019 to 24 October 2019. Lanes Closed : There will be one of two lanes closed.
Posted: October 15, 2019, 4:20 pm
Location : The A5103 southbound between the junctions with the M60 and the M56 . Lane Closures : Lane three will be closed. Reason : Barrier repairs are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 05:00 from 16 October 2019 to 19 October 2019. Lanes Closed : There will be one of four lanes closed.
Posted: October 15, 2019, 4:20 pm
Location : The M60 clockwise between junctions J10 and J11 . Lane Closures : The hard shoulder is closed. Reason : Barrier repairs. Status : Currently Active. Period : expect disruption until 23:59 on 31 December 2019.
Posted: October 15, 2019, 4:20 pm
Location : The A5103 northbound at the junction with the M60 . Lane Closures : Lane three will be closed. Reason : Barrier repairs are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 05:00 from 16 October 2019 to 19 October 2019. Lanes Closed : There will be one of three lanes closed.
Posted: October 15, 2019, 4:20 pm
Location : The M60 clockwise entry slip at junction J2 . Lane Closures : Lane one will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 05:00 from 20 October 2019 to 22 October 2019. Schedule : Expect disruption everyday between 21:00 and 05:00 from 27 October 2019 to 29 October 2019. Schedule : Expect disruption everyday between 21:00 and 05:00 from 3 November 2019 to 8 November 2019. Lanes Closed : There will be one of two lanes closed.
Posted: October 15, 2019, 4:20 pm
Location : The M62 eastbound between junctions J8 and J9 . Reason : Roadworks scheme is planned. Status : Pending. Schedule : From 22:00 on 21 October 2019 to 05:00 on 8 November 2019.
Posted: October 15, 2019, 4:20 pm
Location : The M60 clockwise entry slip at junction J2 . Lane Closures : Lane two will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : From 22:45 on 22 October 2019 to 05:00 on 23 October 2019. Schedule : Expect disruption everyday between 21:00 and 05:00 from 23 October 2019 to 25 October 2019. Schedule : Expect disruption everyday between 21:00 and 05:00 from 29 October 2019 to 1 November 2019. Lanes Closed : There will be one of two lanes closed.
Posted: October 15, 2019, 4:20 pm
Location : The A5103 northbound between the junctions with the M56 and the M60 . Lane Closures : Lane three will be closed. Reason : Barrier repairs are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 05:00 from 16 October 2019 to 19 October 2019. Lanes Closed : There will be one of four lanes closed.
Posted: October 15, 2019, 4:20 pm
Location : The M60 clockwise entry slip at junction J2 . Reason : Roadworks scheme is planned. Status : Pending. Schedule : From 21:00 on 20 October 2019 to 05:00 on 8 November 2019.
Posted: October 15, 2019, 4:20 pm
Location : The A5103 northbound between the junctions with the M56 and the M60 . Lane Closures : Lane three will be closed. Reason : Barrier repairs are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 05:00 from 16 October 2019 to 19 October 2019. Lanes Closed : There will be one of three lanes closed.
Posted: October 15, 2019, 4:20 pm
Location : The M56 westbound between junctions J10 and J11 . Reason : Roadworks scheme is planned. Status : Pending. Schedule : From 21:00 on 21 October 2019 to 06:00 on 23 October 2019.
Posted: October 15, 2019, 4:20 pm
Location : The M56 westbound between junctions J9 and J11 . Lane Closures : Lanes 1, 2 and 3 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 06:00 from 21 October 2019 to 23 October 2019. Lanes Closed : There will be three of four lanes closed.
Posted: October 15, 2019, 4:20 pm
Location : The M6 southbound exit slip at junction J21A to M62 East. Lane Closures : Lane one is closed. Reason : Roadworks. Status : Currently Active. Period : expect disruption until 06:00 on 31 March 2020. Lanes Closed : There is one of two lanes closed.
Posted: October 15, 2019, 4:20 pm
Location : The M62 westbound between junctions J9 and J8 . Reason : Roadworks scheme is planned. Status : Pending. Schedule : From 22:00 on 21 October 2019 to 05:00 on 7 November 2019.
Posted: October 15, 2019, 4:20 pm
Location : The A5103 southbound between the junctions with the M60 and the M56 . Lane Closures : Lane three will be closed. Reason : Barrier repairs are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 05:00 from 16 October 2019 to 19 October 2019. Lanes Closed : There will be one of three lanes closed.
Posted: October 15, 2019, 4:20 pm

Announcements

Breaking News: Traffic Information

Breaking News

The latest current breaking news items for England's motorway network

Regional Twitter feed

Keep up-to-date

Sign up for updates
Please leave feedback