M6 junction 19

We'll be making improvements to junction 19 of the M6.

Region:  North West
Start date:  2019-20
Cost:  £31 million to £66 million
Status:  PLANNED
Type:  Major Scheme
End date:  Summer / Autumn 2021
Programme:  

Have your say

We've introduced a new engagement tool where you can give your views on the project. Please click on the map below to add your comments about specific parts of the route.

Preview image of interactive map for M6 Junction 16 Improvement Scheme

Progress report

We will be starting work on the M6 Junction 19 Improvement scheme in late March 2020. During the first few weeks, the main focus of the work will be within the centre of the roundabout, making preparations to enable us to start building the foundations of the new bridge from late May onwards. Other pockets of work will be carried out at the same time to confirm the location and condition of drainage provision, underground services and power cables.

We will be installing narrow lanes and speed restrictions on the M6 carriageway and within the roundabout. Narrow lanes and a reduced speed limit are required to provide a safe working space for our workers. We advise drivers to take extra care within our roadworks and allow extra time for your journey.

Some closures will be required to install our traffic management. We will not close the motorway and the junction at the same time. If you would like to be added to our traffic management bulletin for information on closures, please contact us at M6Junction19Improvement@highwaysengland.co.uk

We have recently completed our ground investigation work and we’re now starting to set up our compound. The compound will be used as our office, for car parking, and for storage of the materials and construction equipment. The site will be required for approximately 15 months.

The site compound along with the construction activities will inevitably cause some disruption for local residents around the junction, but we will endeavour to minimise the impact where possible. Construction activities will be supervised, keeping disturbance to a minimum, and we will monitor noise levels to ensure they do not reach an unacceptable level.

Ground investigation works taking place within the roundabout

What's next?

During April and May 2020, our main focus of the work will be within the centre of the roundabout, making preparations to enable us to start building the foundations of the new bridge from late May onwards. Other pockets of work will be carried out at the same time to confirm the location and condition of drainage provision, underground services and power cables.

Contact us

If you have any questions about our scheme, please contact us as follows:

Email: M6Junction19Improvement@highwaysengland.co.uk
Telephone: 0300 123 5000 (Customer Contact Centre)
Postal address: M6 J19 Project Team, Highways England, 5th Floor Piccadilly Place, Manchester, M1 3BN

Timeline

Date Event
December 2014 Scheme announced in Road Investment Strategy
7 August to 23 September 2016 Have your say: design options consultation
May 2018 Public information events
2018-20 Finalising scheme design and completing Highways Orders process
January 2020 Public information exhibitions
March 2020 Scheme construction begins
Summer 2020 Improvements to M6 junction 19 roundabout carriageway. Alterations to the A556 Tabley Hill Lane junction. Building the structures required to support the new bridge in the centre of the junction.
Winter 2020 Lifting the bridge beam into place. Bridge deck construction and road surfacing.
September 2021 Construction ends

Why we need this scheme

This busy junction is currently used by around 65,000 vehicles each day and is in need of improvement to meet the expected increase in traffic coming from the M6 and the A556. This increase is further exacerbated by the expansion of Manchester Airport (Airport City) and the development of the Wythenshawe MediPark.

M6 junction 19 improvements are part of a wider collection of schemes to improve connections between Cheshire and South Manchester, including the completed A556 between Knutsford and Bowdon, the improved B5569, the M6 junction 16-19 smart motorway and the planned M56 junction 6-8 smart motorway.

The government announced this scheme in December 2014 as part of the Road Investment Strategy.

Aims

The changes are vital for reducing congestion in the future, improving safety and journey time reliability for all road users and increasing connectivity between local areas. The plans will also improve access for walkers and cyclists.

The scheme in detail

We propose to:

  • add a two-way link across the junction to allow better connection between the M6 and A556, including a new bridge spanning the M6 motorway within the roundabout
  • renew traffic signals on the roundabout and its approach roads
  • add new traffic signals for the Tabley Hill Lane / Pickmere Lane junction
  • add new signs
  • improve local access for walkers and cyclists using the junction

Project media files and documents

There are no images for this project

Project timeline

Planned roadworks

Roadworks and Events for England

The latest incident information for England's motorway and trunk routes provided by Highways England

Location : The M6 northbound at junction J21A . Lane Closures : Lane one will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : From 21:00 on 28 March 2020 to 06:00 on 29 March 2020. Schedule : Expect disruption everyday between 21:00 and 06:00 from 29 March 2020 to 1 April 2020. Lanes Closed : There will be one of four lanes closed.
Posted: March 28, 2020, 7:04 am
Location : The M6 northbound at junction J21A . Lane Closures : Lane one will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : From 21:00 on 28 March 2020 to 06:00 on 29 March 2020. Schedule : Expect disruption everyday between 21:00 and 06:00 from 29 March 2020 to 1 April 2020. Lanes Closed : There will be one of three lanes closed.
Posted: March 28, 2020, 7:01 am
Location : The M62 eastbound between junctions J10 and J11 . Lane Closures : Lanes 1, 2 and 3 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : From 21:00 on 28 March 2020 to 06:00 on 29 March 2020. Schedule : Expect disruption everyday between 21:00 and 06:00 from 29 March 2020 to 1 April 2020. Lanes Closed : All lanes will be closed.
Posted: March 28, 2020, 6:57 am
Location : The M62 eastbound exit slip at junction J11 . Reason : Roadworks are planned. Status : Pending. Schedule : From 21:00 on 28 March 2020 to 06:00 on 29 March 2020. Schedule : Expect disruption everyday between 21:00 and 06:00 from 29 March 2020 to 1 April 2020. Lanes Closed : All lanes will be closed.
Posted: March 28, 2020, 6:53 am
Location : The M6 southbound between junctions J22 and J21A . Lane Closures : Lane one will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : From 21:00 on 28 March 2020 to 06:00 on 29 March 2020. Schedule : Expect disruption everyday between 21:00 and 06:00 from 29 March 2020 to 1 April 2020. Lanes Closed : There will be one of three lanes closed.
Posted: March 28, 2020, 6:51 am
Location : The M6 northbound entry slip at junction J21A from M62 westbound. Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : From 21:00 on 28 March 2020 to 06:00 on 29 March 2020. Schedule : Expect disruption everyday between 21:00 and 06:00 from 29 March 2020 to 1 April 2020. Lanes Closed : All lanes will be closed.
Posted: March 28, 2020, 6:48 am
Location : The M6 southbound entry slip at junction J21A from M62 Westbound. Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : From 21:00 on 28 March 2020 to 06:00 on 29 March 2020. Schedule : Expect disruption everyday between 21:00 and 06:00 from 29 March 2020 to 1 April 2020. Lanes Closed : All lanes will be closed.
Posted: March 28, 2020, 6:46 am
Location : The M62 westbound entry slip at junction J11 . Reason : Roadworks are planned. Status : Pending. Schedule : From 21:00 on 28 March 2020 to 06:00 on 29 March 2020. Schedule : Expect disruption everyday between 21:00 and 06:00 from 29 March 2020 to 1 April 2020. Lanes Closed : All lanes will be closed.
Posted: March 28, 2020, 6:40 am
Location : The M62 westbound between junctions J12 and J10 . Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : From 21:00 on 28 March 2020 to 06:00 on 29 March 2020. Schedule : Expect disruption everyday between 21:00 and 06:00 from 29 March 2020 to 1 April 2020. Lanes Closed : All lanes will be closed.
Posted: March 28, 2020, 6:38 am
Location : The M62 westbound exit slip at junction J11 . Reason : Roadworks are planned. Status : Pending. Schedule : From 21:00 on 28 March 2020 to 06:00 on 29 March 2020. Schedule : Expect disruption everyday between 21:00 and 06:00 from 29 March 2020 to 1 April 2020. Lanes Closed : All lanes will be closed.
Posted: March 28, 2020, 6:38 am
Location : The M62 westbound exit slip at junction J10 . Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : From 21:00 on 28 March 2020 to 06:00 on 29 March 2020. Schedule : Expect disruption everyday between 21:00 and 06:00 from 29 March 2020 to 1 April 2020. Lanes Closed : All lanes will be closed.
Posted: March 28, 2020, 6:36 am
Location : The M6 northbound at junction J21A . Reason : Roadworks are planned. Status : Pending. Schedule : From 21:00 on 28 March 2020 to 06:00 on 29 March 2020. Schedule : Expect disruption everyday between 21:00 and 06:00 from 29 March 2020 to 1 April 2020.
Posted: March 28, 2020, 6:18 am
Location : The M6 northbound at junction J21A . Reason : Roadworks are planned. Status : Pending. Schedule : From 21:00 on 28 March 2020 to 06:00 on 29 March 2020. Schedule : Expect disruption everyday between 21:00 and 06:00 from 29 March 2020 to 1 April 2020.
Posted: March 28, 2020, 6:18 am
Location : The M62 eastbound between junctions J10 and J11 . Reason : Roadworks are planned. Status : Pending. Schedule : From 21:00 on 28 March 2020 to 06:00 on 29 March 2020. Schedule : Expect disruption everyday between 21:00 and 06:00 from 29 March 2020 to 1 April 2020.
Posted: March 28, 2020, 6:13 am
Location : The M62 eastbound exit slip at junction J11 . Reason : Roadworks are planned. Status : Pending. Schedule : From 21:00 on 28 March 2020 to 06:00 on 29 March 2020. Schedule : Expect disruption everyday between 21:00 and 06:00 from 29 March 2020 to 1 April 2020.
Posted: March 28, 2020, 6:12 am
Location : The M6 southbound exit slip at junction J21A to M62 East. Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : From 21:00 on 28 March 2020 to 06:00 on 29 March 2020. Schedule : Expect disruption everyday between 21:00 and 06:00 from 29 March 2020 to 1 April 2020. Lanes Closed : All lanes will be closed.
Posted: March 28, 2020, 6:12 am
Location : The M6 southbound between junctions J22 and J21A . Reason : Roadworks are planned. Status : Pending. Schedule : From 21:00 on 28 March 2020 to 06:00 on 29 March 2020. Schedule : Expect disruption everyday between 21:00 and 06:00 from 29 March 2020 to 1 April 2020.
Posted: March 28, 2020, 6:05 am
Location : The M6 northbound exit slip at junction J21A to M62 east. Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : From 21:00 on 27 March 2020 to 06:00 on 28 March 2020. Schedule : From 21:00 on 28 March 2020 to 06:00 on 29 March 2020. Schedule : Expect disruption everyday between 21:00 and 06:00 from 29 March 2020 to 1 April 2020. Lanes Closed : All lanes will be closed.
Posted: March 28, 2020, 5:38 am
Location : The M62 eastbound between junctions J9 and J10 . Lane Closures : Lane one will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : From 21:00 on 28 March 2020 to 05:00 on 29 March 2020. Schedule : Expect disruption everyday between 21:00 and 05:00 from 29 March 2020 to 3 April 2020. Lanes Closed : All lanes will be closed.
Posted: March 28, 2020, 5:26 am
Location : The M6 southbound exit slip at junction J21A to M62 East. Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : From 21:00 on 28 March 2020 to 06:00 on 29 March 2020. Schedule : Expect disruption everyday between 21:00 and 06:00 from 29 March 2020 to 1 April 2020. Lanes Closed : All lanes will be closed.
Posted: March 28, 2020, 5:09 am
Location : The M62 westbound between junctions J12 and J10 . Reason : Roadworks scheme. Status : Currently Active. Period : from 23:01 on 9 March 2020 to 06:00 on 1 April 2020.
Posted: March 27, 2020, 7:52 pm
Location : The M6 southbound between junctions J21 and J20 . Lane Closures : The hard shoulder is closed. Reason : Emergency barrier repairs. Status : Currently Active. Period : expect disruption until 12:01 on 16 December 2020.
Posted: March 27, 2020, 5:23 pm
Location : The M6 southbound exit slip at junction J21A to M62 East. Lane Closures : Lane one is closed. Reason : Roadworks. Status : Currently Active. Period : expect disruption until 06:00 on 31 March 2020. Lanes Closed : There is one of two lanes closed.
Posted: March 27, 2020, 9:15 am
Location : The M6 southbound between junctions J22 and J21A . Reason : Roadworks scheme. Status : Currently Active. Period : from 21:00 on 16 March 2020 to 06:00 on 1 April 2020.
Posted: March 27, 2020, 8:53 am
Location : The M62 eastbound between junctions J9 and J10 . Reason : Roadworks scheme. Status : Currently Active. Period : from 21:01 on 26 March 2020 to 05:00 on 3 April 2020.
Posted: March 26, 2020, 9:02 pm
Location : The M56 eastbound at junction J6 . Lane Closures : Lane one will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 05:00 from 30 March 2020 to 4 April 2020. Lanes Closed : There will be one of three lanes closed.
Posted: March 26, 2020, 5:21 am
Location : The M56 eastbound between junctions J7 and J6 . Lane Closures : Lane one will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 05:00 from 30 March 2020 to 4 April 2020. Lanes Closed : There will be one of four lanes closed.
Posted: March 26, 2020, 5:21 am
Location : The M56 eastbound at junction J7 . Lane Closures : Lane one will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 05:00 from 30 March 2020 to 4 April 2020. Lanes Closed : There will be one of three lanes closed.
Posted: March 26, 2020, 5:20 am
Location : The M56 eastbound entry slip at junction J7 . Lane Closures : Lane one will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 05:00 from 30 March 2020 to 4 April 2020. Lanes Closed : There will be one of two lanes closed.
Posted: March 26, 2020, 5:17 am
Location : The M56 westbound at junction J6 . Lane Closures : Lane one will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 05:00 from 30 March 2020 to 4 April 2020. Lanes Closed : There will be one of three lanes closed.
Posted: March 26, 2020, 5:17 am
Location : The M56 westbound at junction J7 . Lane Closures : Lane one will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 05:00 from 30 March 2020 to 4 April 2020. Lanes Closed : There will be one of three lanes closed.
Posted: March 26, 2020, 5:17 am
Location : The M56 westbound between junctions J6 and J7 . Lane Closures : Lane one will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 05:00 from 30 March 2020 to 4 April 2020. Lanes Closed : There will be one of four lanes closed.
Posted: March 26, 2020, 5:17 am
Location : The M56 westbound at junction J5 . Lane Closures : Lane one will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 05:00 from 30 March 2020 to 4 April 2020. Lanes Closed : There will be one of three lanes closed.
Posted: March 26, 2020, 5:13 am
Location : The M56 westbound between junctions J5 and J6 . Lane Closures : Lane one will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 05:00 from 30 March 2020 to 4 April 2020. Lanes Closed : There will be one of four lanes closed.
Posted: March 26, 2020, 5:13 am
Location : The M56 eastbound between junctions J7 and J6 . Reason : Roadworks scheme. Status : Currently Active. Period : from 20:34 on 25 March 2020 to 05:00 on 4 April 2020.
Posted: March 25, 2020, 8:35 pm
Location : The M56 westbound between junctions J5 and J7 . Reason : Roadworks scheme. Status : Currently Active. Period : from 20:34 on 25 March 2020 to 05:00 on 4 April 2020.
Posted: March 25, 2020, 8:35 pm
Location : The M62 westbound between junctions J10 and J9 . Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 08:00 and 17:00 from 30 March 2020 to 1 April 2020.
Posted: March 25, 2020, 5:58 pm
Location : The M6 northbound at junction J19 . Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 06:00 from 29 March 2020 to 4 April 2020. Lanes Closed : There will be two of three lanes closed.
Posted: March 25, 2020, 5:23 pm
Location : The M6 northbound between junctions J18 and J19 . Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 06:00 from 29 March 2020 to 4 April 2020. Lanes Closed : There will be two of four lanes closed.
Posted: March 25, 2020, 5:23 pm
Location : The M56 westbound between junctions J9 and J11 . Reason : Roadworks scheme is planned. Status : Pending. Schedule : From 20:00 on 30 March 2020 to 05:00 on 29 May 2020.
Posted: March 25, 2020, 3:17 pm
Location : The M56 eastbound between junctions J11 and J9 . Lane Closures : Lanes 2 and 3 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : From 20:00 on 30 March 2020 to 05:00 on 31 March 2020. Lanes Closed : There will be two of three lanes closed.
Posted: March 25, 2020, 3:17 pm
Location : The M56 westbound between junctions J9 and J11 . Lane Closures : Lanes 2 and 3 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 20:00 and 05:00 from 31 March 2020 to 4 April 2020. Schedule : Expect disruption everyday between 20:00 and 05:00 from 6 April 2020 to 9 April 2020. Schedule : Expect disruption everyday between 20:00 and 05:00 from 15 April 2020 to 18 April 2020. Schedule : Expect disruption everyday between 20:00 and 05:00 from 20 April 2020 to 25 April 2020. Lanes Closed : There will be two of three lanes closed.
Posted: March 25, 2020, 3:17 pm
Location : The M56 westbound between junctions J10 and J11 . Lane Closures : Lanes 2 and 3 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : From 20:00 on 30 March 2020 to 05:00 on 31 March 2020. Lanes Closed : There will be two of three lanes closed.
Posted: March 25, 2020, 3:17 pm
Location : The M56 eastbound between junctions J12 and J9 . Lane Closures : Lanes 2 and 3 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 20:00 and 05:00 from 31 March 2020 to 4 April 2020. Schedule : Expect disruption everyday between 20:00 and 05:00 from 6 April 2020 to 9 April 2020. Schedule : Expect disruption everyday between 20:00 and 05:00 from 15 April 2020 to 18 April 2020. Schedule : Expect disruption everyday between 20:00 and 05:00 from 20 April 2020 to 25 April 2020. Lanes Closed : There will be two of three lanes closed.
Posted: March 25, 2020, 3:17 pm
Location : The M56 eastbound between junctions J12 and J9 . Reason : Roadworks scheme is planned. Status : Pending. Schedule : From 20:00 on 30 March 2020 to 05:00 on 29 May 2020.
Posted: March 25, 2020, 3:17 pm
Location : The M6 southbound at junction J20A . Lane Closures : Lanes 1, 2, 3 and 4 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : From 21:00 on 29 March 2020 to 05:00 on 30 March 2020. Lanes Closed : All lanes will be closed.
Posted: March 24, 2020, 11:00 am
Location : The M62 westbound between junctions J12 and J11 . Lane Closures : Lane three is closed. Reason : Roadworks. Status : Currently Active. Period : expect disruption until 06:00 on 31 March 2020. Lanes Closed : There is one of four lanes closed.
Posted: March 24, 2020, 11:00 am
Location : The M6 southbound entry slip at junction J20A from M56 east. Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : From 21:00 on 29 March 2020 to 05:00 on 30 March 2020. Lanes Closed : All lanes will be closed.
Posted: March 24, 2020, 11:00 am
Location : The M6 northbound between junctions J18 and J19 . Reason : Roadworks scheme is planned. Status : Pending. Schedule : From 21:00 on 29 March 2020 to 06:00 on 4 April 2020.
Posted: March 24, 2020, 11:00 am
Location : The M6 southbound between junctions J21 and J20 . Lane Closures : Lanes 2, 3 and 4 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : From 21:00 on 29 March 2020 to 05:00 on 30 March 2020. Lanes Closed : There will be three of four lanes closed.
Posted: March 24, 2020, 11:00 am
Location : The M6 southbound exit slip at junction J19 . Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : From 21:00 on 29 March 2020 to 05:00 on 30 March 2020. Lanes Closed : All lanes will be closed.
Posted: March 24, 2020, 11:00 am
Location : The M6 southbound between junctions J20 and J19 . Reason : Roadworks are planned. Status : Pending. Schedule : From 21:00 on 29 March 2020 to 05:00 on 30 March 2020. Lanes Closed : All lanes will be closed.
Posted: March 24, 2020, 11:00 am
Location : The M6 southbound between junctions J19 and J18 . Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : From 21:00 on 28 March 2020 to 06:00 on 29 March 2020. Lanes Closed : There will be two of four lanes closed.
Posted: March 24, 2020, 11:00 am
Location : The M6 northbound exit slip at junction J21A to M62 east. Reason : Roadworks scheme. Status : Currently Active. Period : from 21:00 on 16 March 2020 to 06:00 on 1 April 2020.
Posted: March 24, 2020, 11:00 am
Location : The M60 anticlockwise between junctions J5 and J4 . Lane Closures : The hard shoulder is closed. Reason : Barrier repairs. Status : Currently Active. Period : expect disruption until 23:59 on 31 December 2020.
Posted: March 24, 2020, 11:00 am
Location : The M6 southbound exit slip at junction J21A to M62 West. Lane Closures : Lane two is closed. Reason : Roadworks. Status : Currently Active. Period : expect disruption until 23:59 on 31 March 2020. Lanes Closed : There is one of two lanes closed.
Posted: March 24, 2020, 11:00 am
Location : The M6 southbound between junctions J20A and J19 . Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : From 21:00 on 28 March 2020 to 06:00 on 29 March 2020. Lanes Closed : There will be two of three lanes closed.
Posted: March 24, 2020, 11:00 am
Location : The M6 southbound exit slip at junction J19 . Reason : Roadworks scheme is planned. Status : Pending. Schedule : From 21:00 on 29 March 2020 to 05:00 on 30 March 2020.
Posted: March 24, 2020, 11:00 am
Location : The M6 northbound exit slip at junction J21A to M62 east. Lane Closures : Lane one is closed. Reason : Roadworks. Status : Currently Active. Period : expect disruption until 06:00 on 31 March 2020. Lanes Closed : There is one of two lanes closed.
Posted: March 24, 2020, 11:00 am
Location : The M6 southbound between junctions J20A and J19 . Lane Closures : The hard shoulder is closed. Reason : Roadworks. Status : Currently Active. Period : expect disruption until 15:30 on 30 April 2020.
Posted: March 24, 2020, 11:00 am

Announcements

Breaking News: Traffic Information

Breaking News

The latest current breaking news items for England's motorway network

Regional Twitter feed

Keep up-to-date

Sign up for updates
Please leave feedback