M5 junction 1 to 2 Oldbury viaduct

Major concrete repair and waterproofing on the M5 Oldbury viaduct, between junctions 1 and 2.

Region:  West Midlands
Start date:  16 January 2017
Cost:  TBC
Status:  CURRENT
Type:  Maintenance Scheme
End date:  Autumn 2019
Programme:  

Progress report

We’ve finished all concrete repairs on the central reservation and will be carrying out waterproofing, surfacing and other work such as concrete barrier installation until the end of November, subject to weather conditions.

Once that is complete, it will take approximately one week to remove the traffic management and fully reopen the M5 J1 – 2, which means motorists will once again benefit from three lanes of traffic (and a hard shoulder) in each direction.

A temporary speed limit will need to remain in place until technology testing is complete. It will then take a further 2 weeks to remove the lane restriction at M6 J8 and 50mph zone on the northbound approach to the viaduct.

We’ll need some overnight closures to complete the work and will keep you updated about when these are taking place.

We recognise the impact this scheme is having on your journeys and appreciate your frustration that work is still ongoing. Thank you for your patience while we carry out this important work.

What's next?

The next phase of work will include:

  • completion of drainage
  • upgrading 1km of central barrier to the more modern concrete type
  • re-install the steel barrier which was removed to be able to carry out concrete repairs
  • waterproofing and resurfacing
  • road marking
  • complete the installation of three new gantries and refurbishing the three currently in place
  • upgrades to the drainage underneath the central reservation
  • removal of a large amount of scaffolding underneath the structure

Once we complete the main work, we’ll only need overnight closures to complete the work to the gantries.

Timeline

Date Event
January 2017 Enabling work started
March 2017 Public information events held
April 2017 Three narrow lanes installed between junctions 1 and 2 with 40mph speed limit on the viaduct
August 2017 Contraflow system installed and start of concrete repair works
September 2018 Work switches from the southbound to the northbound carriageway
January 2019 Removal of traffic management at M5 junction 4a
Summer 2019 Removal of contraflow and change to two narrow lanes on each carriageway along the viaduct
Autumn 2019 Completion of main work, return to three lanes on each carriageway along the viaduct and remove other traffic management measures

Why we need this scheme

The M5 is one of the busiest routes in the country, carrying a mix of traffic through the Midlands and onwards to routes in the north and south. This section of the M5 is particularly busy, with traffic joining with the M6 and other roads into and out of the Birmingham hub.

Oldbury viaduct carries approximately 1.8 miles of the elevated sections of the M5 to the west of Birmingham between junctions 1 and 2. The structure is safe, but we need to carry out essential repair work to deteriorated concrete due to its perished waterproofing.

The decision to repair this section of motorway now was based on both its condition and to avoid large-scale projects occurring at the same time around the ‘Birmingham Box’ (M5/M42/M6) over the next few years. We have kept the slip roads open and have restricted the occasional closure of slip roads, carriageway and local roads to the night-time only. We have kept open most of the public walkways underneath.

This work is part of the government’s long-term Road Investment Strategy to build a modern and resilient road network. By maintaining this key corridor, we will support economic growth locally and across the West Midlands.

The scheme in detail

The scheme is a very significant infrastructure project for the West Midlands, and is the largest concrete repair project in the UK for many years.

The viaduct is 1.8 miles long and was constructed in the late 1960’s. It is part of what was known as the Midland Links Motorway. It passes over the conurbation of Sandwell and its usage has grown to 60,000 vehicles per day in each direction. It has several interfaces with local roads, canals and railway and tram lines.

The viaduct is split into 165 separate sections which are linked by joints fitted in the gap between the ends of two sections. On the top of each section is a concrete slab, or deck, which is reinforced by meshes of steel embedded within. The deck has a long maintenance cycle compared to its supporting structures which are in good condition. A waterproofing layer protects a deck from the motorway’s run-off water, but this layer has perished over time, resulting in damage to the concrete and some corrosion of its steel reinforcement.

We have kept the programme to a minimum by repairing a whole carriageway at a time, starting with the southbound carriageway. This approach separates the workforce from live traffic and provides us with operational flexibility. Other approaches would increase timescales and the disruption to our customers overall. The work is complicated and needs a great deal of planning and safety considerations.

If you're travelling across the country or into and around Birmingham, we encourage you to consider alternative routes on our network, such as the M42 and M6 or M6 Toll. This will reduce the amount of traffic heading through the roadworks in this busy part of the network and will reduce the impact on local roads.

To help with this, we've made changes to the road layout at key junctions in the area, including at M6 junction 8 southbound and M5 junction 4a northbound.

These roadworks are causing some disruption to the M5 and the local area. We would like to thank you for your patience and recommend that where possible you:

  • plan ahead
  • allow extra time for your journeys
  • consider using alternative routes
  • change modes of transport
  • car share
  • work from home

View information on local public transport alternatives.

View information on other work in the Birmingham area.

View information on the M6 Toll.

Traffic study

We regularly review network performance, resilience and recovery. Based on this, we altered our traffic management strategy and reinstated two lanes northbound at M5 junction 4a in January 2019. More recently, we shortened the distance of the 50mph speed restriction on the northbound approach to M5 junction 2 by over a mile. Monitoring continues to show that the restriction at M6 junction 8 is effective.

The different measures in place combine to manage traffic flows safely and minimise the disruption on the M5 corridor, as well as local roads, towns and villages.

View the traffic management assessment - July 2017 to May 2018

View the traffic management assessment - July to October 2017

Project media files and documents

There are no videos for this project

Project timeline

Planned roadworks

Roadworks and Events for England

The latest incident information for England's motorway and trunk routes provided by Highways England

Location : The M5 northbound between junctions J3 and J2 . Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 20:00 and 06:00 from 19 September 2019 to 21 September 2019. Schedule : From 20:00 on 27 September 2019 to 06:00 on 28 September 2019. Schedule : Expect disruption everyday between 20:00 and 06:00 from 30 September 2019 to 5 October 2019. Schedule : Expect disruption everyday between 20:00 and 06:00 from 7 October 2019 to 12 October 2019. Lanes Closed : All lanes will be closed.
Posted: September 19, 2019, 11:14 am
Location : The M5 northbound between junctions J2 and J1 . Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 20:00 and 06:00 from 19 September 2019 to 21 September 2019. Schedule : From 20:00 on 27 September 2019 to 06:00 on 28 September 2019. Schedule : Expect disruption everyday between 20:00 and 06:00 from 30 September 2019 to 5 October 2019. Schedule : Expect disruption everyday between 20:00 and 06:00 from 7 October 2019 to 12 October 2019. Lanes Closed : All lanes will be closed.
Posted: September 19, 2019, 11:14 am
Location : The M5 northbound exit slip at junction J1 . Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 20:00 and 06:00 from 19 September 2019 to 21 September 2019. Schedule : From 20:00 on 27 September 2019 to 06:00 on 28 September 2019. Schedule : Expect disruption everyday between 20:00 and 06:00 from 30 September 2019 to 5 October 2019. Schedule : Expect disruption everyday between 20:00 and 06:00 from 7 October 2019 to 12 October 2019. Lanes Closed : All lanes will be closed.
Posted: September 19, 2019, 11:14 am
Location : The M5 southbound between the M6 and junction J3 . Lane Closures : Lanes 1, 2 and 3 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 20:00 and 06:00 from 23 September 2019 to 28 September 2019. Schedule : From 20:00 on 21 October 2019 to 06:00 on 22 October 2019. Schedule : From 23:30 on 22 October 2019 to 06:00 on 23 October 2019. Schedule : Expect disruption everyday between 20:00 and 06:00 from 23 October 2019 to 26 October 2019. Lanes Closed : All lanes will be closed.
Posted: September 19, 2019, 11:14 am
Location : The M5 southbound exit slip at junction J2 . Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 20:00 and 06:00 from 23 September 2019 to 28 September 2019. Schedule : From 20:00 on 21 October 2019 to 06:00 on 22 October 2019. Schedule : From 23:30 on 22 October 2019 to 06:00 on 23 October 2019. Schedule : Expect disruption everyday between 20:00 and 06:00 from 23 October 2019 to 26 October 2019. Lanes Closed : All lanes will be closed.
Posted: September 19, 2019, 11:14 am
Location : The M5 southbound entry slip at junction J1 . Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 20:00 and 06:00 from 23 September 2019 to 28 September 2019. Schedule : From 20:00 on 21 October 2019 to 06:00 on 22 October 2019. Schedule : From 23:30 on 22 October 2019 to 06:00 on 23 October 2019. Schedule : Expect disruption everyday between 20:00 and 06:00 from 23 October 2019 to 26 October 2019. Lanes Closed : All lanes will be closed.
Posted: September 19, 2019, 11:14 am
Location : The M5 northbound between junctions J3 and J2 . Reason : Roadworks scheme is planned. Status : Pending. Schedule : From 20:00 on 19 September 2019 to 06:00 on 8 November 2019.
Posted: September 19, 2019, 10:43 am
Location : The M5 southbound between the M6 and junction J3 . Reason : Roadworks scheme is planned. Status : Pending. Schedule : From 20:00 on 23 September 2019 to 06:00 on 30 November 2019.
Posted: September 19, 2019, 10:43 am
Location : The M5 southbound between junctions J1 and J2 . Lane Closures : Lane two is closed. Reason : Road repairs. Status : Currently Active. Period : expect disruption until 06:00 on 20 December 2019. Lanes Closed : There is one of two lanes closed.
Posted: September 19, 2019, 8:50 am
Location : The M5 northbound between junctions J3 and J1 . Lane Closures : Lane two is closed. Reason : Road repairs. Status : Currently Active. Period : expect disruption until 06:00 on 20 December 2019. Lanes Closed : There is one of two lanes closed.
Posted: September 19, 2019, 5:37 am
Location : The M5 northbound between junctions J3 and J2 . Lane Closures : The hard shoulder and lane 1 are closed. Reason : Road repairs. Status : Currently Active. Period : expect disruption until 06:00 on 20 December 2019. Lanes Closed : There is one of two lanes closed.
Posted: September 19, 2019, 5:16 am
Location : The M5 southbound between junctions J2 and J3 . Lane Closures : Lanes 2 and 3 are closed. Reason : Road repairs. Status : Currently Active. Period : expect disruption until 06:00 on 20 December 2019. Lanes Closed : There are two of three lanes closed.
Posted: September 19, 2019, 5:05 am

Announcements

Breaking News: Traffic Information

Breaking News

The latest current breaking news items for England's motorway network

Regional Twitter feed

Keep up-to-date

Sign up for updates
Please leave feedback