M1 junction 45 improvement scheme

Works to widen the slip roads and roundabout to increase capacity at this junction.

Region:  North East
Start date:  31 January 2017
Cost:  ÂŁ8.3 million
Status:  CURRENT
Type:  Improvement Scheme
End date:  December 2017
Programme:  

Progress report

We will start work on this scheme on 31 January 2017. Our contractors, Interserve, will be carrying out the work on our behalf.

What's next?

We’ll be widening some of the entry and exit slip roads to the roundabout at junction 45 of the M1 and adding an extra lane to the roundabout itself increasing it from 2 to 3 lanes. This will improve capacity at the junction which is a major route in and out of Leeds city centre.

We’ll need to close the road so we can carry out important bridge works, gantry installation and road surfacing.

Use our roadworks tool to check for forthcoming closures.

Timeline

Event Date
Work starts 31 January 2017
Work ends December 2017

Cyclists, horse riders, pedestrians

During the works we will extend the underpass under the M1 to Temple Newsam. We will work to make sure this underpass stays open at all times. When works are taking place on the underpass, one of our contractor Interserve’s staff will make sure you are escorted through safely.

On completion of the scheme we will have created a route for pedestrians and cyclists to cross between Pontefract Lane to the north and south of the junction, using Toucan pedestrian and cycle crossings.

Why we need the scheme

The M1 is an important north-south link. Junction 45 serves east Leeds and currently suffers from congestion, particularly at peak times. If we don’t act now, this situation will get worse.

The extra capacity will also be needed to support developments planned in this area, particularly along the East Leeds Link Road, which is part of the Aire Valley Enterprise Zone.

Aims

With this scheme, we aim to:

  • reduce existing delays
  • open up new areas for development
  • encourage economic growth and job creation

Project media files and documents

There are no images for this project
There are no videos for this project

Project timeline

Planned roadworks

Roadworks and Events for England

The latest incident information for England's motorway and trunk routes provided by Highways England

Location : The M1 northbound entry slip at junction J42 . Lane Closures : Lane one will be closed. Reason : Emergency barrier repairs are planned. Status : Pending. Schedule : Expect disruption everyday between 22:00 and 06:00 from 31 March 2020 to 2 April 2020. Lanes Closed : There will be one of two lanes closed.
Posted: March 25, 2020, 3:49 pm
Location : The M62 westbound between junctions J30 and J29 . Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : From 20:00 on 29 March 2020 to 06:00 on 30 March 2020. Lanes Closed : There will be two of four lanes closed.
Posted: March 25, 2020, 2:33 pm
Location : The M621 eastbound between the M62 and junction J1 . Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadside equipment maintenance is planned. Status : Pending. Schedule : From 20:00 on 31 March 2020 to 06:00 on 1 April 2020. Lanes Closed : All lanes will be closed.
Posted: March 25, 2020, 1:18 pm
Location : The M1 southbound between junctions J45 and J44 . Lane Closures : Lanes 1, 2 and 3 will be closed. Reason : Bridge repairs are planned. Status : Pending. Schedule : Expect disruption everyday between 19:00 and 06:00 from 3 April 2020 to 6 April 2020. Lanes Closed : All lanes will be closed.
Posted: March 25, 2020, 11:55 am
Location : The M1 southbound entry slip at junction J45 . Reason : Bridge repairs are planned. Status : Pending. Schedule : Expect disruption everyday between 19:00 and 06:00 from 3 April 2020 to 6 April 2020. Lanes Closed : All lanes will be closed.
Posted: March 25, 2020, 11:55 am
Location : The M1 southbound exit slip at junction J44 . Reason : Bridge repairs are planned. Status : Pending. Schedule : Expect disruption everyday between 19:00 and 06:00 from 3 April 2020 to 6 April 2020. Lanes Closed : All lanes will be closed.
Posted: March 25, 2020, 11:55 am
Location : The M621 eastbound entry slip at junction J5 . Reason : Barrier repairs are planned. Status : Pending. Schedule : Expect disruption everyday between 20:00 and 06:00 from 30 March 2020 to 3 April 2020. Schedule : Expect disruption everyday between 20:00 and 06:00 from 6 April 2020 to 9 April 2020. Lanes Closed : All lanes will be closed.
Posted: March 25, 2020, 11:22 am
Location : The M621 eastbound entry slip at junction J4 . Reason : Barrier repairs are planned. Status : Pending. Schedule : Expect disruption everyday between 20:00 and 06:00 from 30 March 2020 to 3 April 2020. Schedule : Expect disruption everyday between 20:00 and 06:00 from 6 April 2020 to 9 April 2020. Lanes Closed : All lanes will be closed.
Posted: March 25, 2020, 11:22 am
Location : The M621 eastbound exit slip at junction J4 . Lane Closures : Lane one will be closed. Reason : Barrier repairs are planned. Status : Pending. Schedule : Expect disruption everyday between 20:00 and 06:00 from 30 March 2020 to 3 April 2020. Schedule : Expect disruption everyday between 20:00 and 06:00 from 6 April 2020 to 9 April 2020. Lanes Closed : All lanes will be closed.
Posted: March 25, 2020, 11:21 am
Location : The M621 eastbound exit slip at junction J6 . Lane Closures : Lanes 1 and 2 will be closed. Reason : Barrier repairs are planned. Status : Pending. Schedule : Expect disruption everyday between 20:00 and 06:00 from 30 March 2020 to 3 April 2020. Schedule : Expect disruption everyday between 20:00 and 06:00 from 6 April 2020 to 9 April 2020. Lanes Closed : All lanes will be closed.
Posted: March 25, 2020, 11:21 am
Location : The M621 eastbound exit slip at junction J7 . Reason : Barrier repairs are planned. Status : Pending. Schedule : Expect disruption everyday between 20:00 and 06:00 from 30 March 2020 to 3 April 2020. Schedule : Expect disruption everyday between 20:00 and 06:00 from 6 April 2020 to 9 April 2020. Lanes Closed : All lanes will be closed.
Posted: March 25, 2020, 11:21 am
Location : The M621 eastbound between junctions J2 and J7 . Lane Closures : Lanes 1 and 2 will be closed. Reason : Barrier repairs are planned. Status : Pending. Schedule : Expect disruption everyday between 20:00 and 06:00 from 30 March 2020 to 3 April 2020. Schedule : Expect disruption everyday between 20:00 and 06:00 from 6 April 2020 to 9 April 2020. Lanes Closed : All lanes will be closed.
Posted: March 25, 2020, 11:21 am
Location : The M621 westbound exit slip at junction J7 . Lane Closures : Lane one will be closed. Reason : Road repairs are planned. Status : Pending. Schedule : Expect disruption everyday between 20:00 and 06:00 from 30 March 2020 to 4 April 2020. Schedule : Expect disruption everyday between 20:00 and 06:00 from 6 April 2020 to 9 April 2020. Schedule : Expect disruption everyday between 20:00 and 06:00 from 14 April 2020 to 18 April 2020. Schedule : Expect disruption everyday between 20:00 and 06:00 from 20 April 2020 to 25 April 2020. Lanes Closed : There will be one of two lanes closed.
Posted: March 24, 2020, 11:00 am
Location : The M621 westbound exit slip at junction J7 . Lane Closures : The hard shoulder is closed. Reason : Road repairs. Status : Currently Active. Period : expect disruption until 20:00 on 30 March 2020.
Posted: March 24, 2020, 11:00 am
Location : The M621 eastbound exit slip at junction J7 . Lane Closures : Lane one is closed. Reason : Roadworks. Status : Currently Active. Period : expect disruption until 06:00 on 11 April 2020. Lanes Closed : There is one of two lanes closed.
Posted: March 24, 2020, 11:00 am
Location : The M621 eastbound exit slip at junction J7 . Reason : Roadworks scheme. Status : Currently Active. Period : from 09:32 on 27 November 2019 to 06:00 on 11 April 2020.
Posted: March 24, 2020, 11:00 am

Announcements

Breaking News: Traffic Information

Breaking News

The latest current breaking news items for England's motorway network

Regional Twitter feed

Keep up-to-date

Sign up for updates
Please leave feedback