A23 Brighton Road Hooley improvementsRecently updated

Proposed scheme to improve congestion and safety on the A23 Brighton Road, Hooley, Surrey.

Region:  South East
Start date:  Summer 2019
Cost:  ÂŁ3.8 million
Status:  PLANNED
Type:  Improvement Scheme
End date:  Spring 2020
Programme:  

Progress report

We are currently in the process of developing the design of the scheme and we are undertaking surveys to identify existing highway issues to help inform us in completing this design.

The survey works started on the 11 June 2018 and will take around eight weeks to complete. The work will be completed overnight between 10pm and 5am, Monday to Thursday (inclusive). On Friday nights, work will take place between 11pm and 6am. Works throughout the day will take place between 8am and 5pm. To deliver the survey work safely, traffic overnight will be controlled using temporary traffic lights.

Please note, dates and times are subject to change. Please check the Roadworks section below for more details.

What's next?

We will be holding a public information event in Hooley, where more information on the proposed scheme will be available. The event will be held over two days at Hooley Village Hall, St Margaret’s Road, Hooley Village, Coulsdon, Surrey, CR5 3RB.

Date Time
Friday 27 July 2018 8:30am to 12noon and 4pm to 7pm
Saturday 28 July 2018 9am to 11:30am

Comments received during this event will be considered while preparing the final design and determine the next steps. If a scheme is taken forward, individual residents will be contacted if there are issues directly relating to their property.

Timeline

Date Event
July 2018 Public information events
December 2018 Complete detailed design
Summer 2019 (TBC) Start of construction works
Spring 2020 (TBC) Planned completion of the works

Why we need this scheme

The A23 Brighton Road through Hooley is a strategic route between Brighton and London, and is a key route for motorists travelling to and from Gatwick Airport.

The proposed scheme will ease congestion, improve safety and provide better links for pedestrians and cyclists.

Aims

  • reduce accident rates
  • reduce congestion
  • improve traffic flow
  • improve provision for cyclists and pedestrians

The scheme in detail

Proposed improvements include:

  • reduction in speed limit from 40mph to 30mph through residential area
  • upgrade and synchronise the existing traffic signal timings through the crossroads of the A23 with Netherne Drive and Star Lane
  • new shared footway/cycleway along the A23
  • widen the A23 northbound to two lanes from Church Lane to Netherne Drive
  • widen the A23 southbound to two lanes from Netherne Drive to the Esso garage

Environmental information

We are aware that Hooley is in an Air Quality Management Area and the scheme will ensure there is no detriment to air quality.

Project media files and documents

There are no videos for this project

Project timeline

Planned roadworks

Roadworks and Events for England

The latest incident information for England's motorway and trunk routes provided by Highways England

Location : The M25 clockwise between junctions J8 and J9 . Lane Closures : Lanes 1, 2 and 3 will be closed. Reason : Emergency barrier repairs are planned. Status : Pending. Schedule : Expect disruption everyday between 22:00 and 05:30 from 14 August 2018 to 16 August 2018. Lanes Closed : There will be three of four lanes closed.
Posted: August 14, 2018, 4:30 am
Location : The M25 anticlockwise between junctions J10 and J9 . Lane Closures : Lane one will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 22:00 and 05:00 from 20 August 2018 to 24 August 2018. Lanes Closed : There will be one of four lanes closed.
Posted: August 13, 2018, 9:11 pm
Location : The M25 anticlockwise between junctions J6 and J5 . Lane Closures : Lane one will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : From 22:00 on 14 August 2018 to 05:30 on 15 August 2018. Lanes Closed : There will be one of four lanes closed.
Posted: August 13, 2018, 9:11 pm
Location : The M25 anticlockwise between junctions J10 and J9 . Lane Closures : Lane one will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 22:00 and 05:00 from 20 August 2018 to 24 August 2018. Lanes Closed : There will be one of four lanes closed.
Posted: August 13, 2018, 9:11 pm
Location : The M25 anticlockwise between junctions J6 and J5 . Lane Closures : Lanes 1 and 2 will be closed. Reason : Roadside drains works are planned. Status : Pending. Schedule : Expect disruption everyday between 22:00 and 05:00 from 20 August 2018 to 24 August 2018. Lanes Closed : There will be two of four lanes closed.
Posted: August 13, 2018, 9:10 pm
Location : The M25 anticlockwise between junctions J10 and J9 . Lane Closures : The hard shoulder is closed. Reason : Barrier repairs. Status : Currently Active. Period : expect disruption until 23:59 on 30 November 2018.
Posted: August 13, 2018, 9:04 pm

Announcements

Breaking News: Traffic Information

Breaking News

The latest current breaking news items for England's motorway network

Regional Twitter feed

Keep up-to-date

Sign up for updates
Please leave feedback