A160/A180 Port of Immingham

Improving the A160 between the junction with the A180 at Brocklesby interchange and access to the Port of Immingham.

Region:  North East
Start date:  Spring 2015
Cost:  ¬£96.6 million
Status:  COMPLETED
Type:  Major Scheme
End date:  Spring 2017
Programme:  

Progress report

The new gyratory at Rosper Road is now fully open to traffic. The original single carriageway section of the A160 between Brocklesby junction and Habrough roundabout is now open for use as a dual carriageway and the slip roads at Brocklesby junction are also open.

The new Town Street bridge over the A160 is now open at South Killingholme improving access for residents on both sides of the village.

We currently have off peak lane closures in place midweek with some weekend closures to avoid substantial impact on traffic movement. Check our roadworks calendar for for current roadworks.

What next?

The contractors are continuing to finish the landscaping works and outstanding defects as well as reinstating the land back to previous owners.

Timeline

Date Event
8 April 2013 to 20 May 2013 Pre-application consultation
8 January 2014 Development consent order application submitted
15 to 17 July 2014 Development consent order hearings held
4 September 2014 Closure of development consent order examination
6 November 2014 Inspector's recommendation made
27 and 28 February 2015 Pre-construction exhibition
Spring 2015 Start of works
Spring 2017 Completion of works

Why we need this scheme

This is an important strategic route, yet currently experiences congestion ‚Äď particularly along the single carriageway section ‚Äď due to the very high proportion of heavy goods vehicles.

The scheme in detail

The length of the project is approximately 5km and the main aspects include:
  • upgrading Brocklesby interchange to an oval two bridge roundabout layout, including a dedicated left turn lane for vehicles travelling from the eastbound A180 to the A160
  • upgrading the single carriageway section of the A160 to dual carriageway standard
  • relocating Habrough roundabout to the west of its current position, with new link roads provided from the A160 to Ulceby Road, Top Road and Habrough Road
  • closing the central reserve gap at the junction with Town Street and partially closing the gap at the entrance to the oil refinery
  • provision of a new road bridge at Town Street to provide vehicle and pedestrian access between the two parts of South Killingholme
  • provision of a new gyratory carriageway system between Manby Road roundabout, Rosper Road junction and the Port of Immingham, requiring the construction of a new link road and bridge beneath the railway
  • localised diversion of third-party gas pipelines that cross beneath the existing A160
View a flythrough of the scheme

Aims

We aim to stimulate growth and unlock economic benefits in the area by:
  • reducing traffic congestion
  • improving journey time reliability
  • meet the demands of the predicted growth in traffic resulting from existing and future developments nearby
  • improve safety for road users and the local community

Environmental impact

Staff on the A160 Port of Immingham Improvement Scheme are promoting a ‚ÄėBees Needs‚Äô approach to bumblebee conservation. The team have adopted a ‚ÄėBe Safe Bee Friendly‚Äô approach to the endangered British bumblebee. The A160 team invited Gill Perkins, the Conservation Manager for the Bumblebee Conservation Trust to speak and conduct a bumblebee walk through the project‚Äôs specially constructed water vole habitat.

Gill was delighted with what she found describing the water vole habitat as a ‚Äúbumblebee heaven‚ÄĚ stating ‚ÄúI have never seen so many bumblebees together in one place‚ÄĚ.

Having registered with the Conservation Trust, the A160 team are now looking to encourage local schools and landowners to register with the Bumblebee Conservation Trust to build and maintain bumblebee friendly habitats.

Project media files and documents

There are no images for this project

Project timeline

Planned roadworks

Roadworks and Events for England

The latest incident information for England's motorway and trunk routes provided by Highways England

Location : The A180 eastbound entry slip from the A1173 . Lane Closures : Lane one will be closed. Reason : Litter clearance is planned. Status : Pending. Schedule : From 09:00 on 25 June 2018 to 15:00 on 25 June 2018. Lanes Closed : There will be one of two lanes closed.
Posted: June 22, 2018, 10:50 am
Location : The A1033 eastbound. Lane Closures : Lane one will be closed. Reason : Roadside drains works are planned. Status : Pending. Schedule : From 21:00 on 27 June 2018 to 05:00 on 28 June 2018. Lanes Closed : There will be one of two lanes closed.
Posted: June 22, 2018, 9:09 am
Location : The A63 westbound between the junctions with the A1079 and the A1166 . Lane Closures : Lane one is closed. Reason : Road repairs. Status : Currently Active. Period : expect disruption until 19:00 on 31 August 2018. Lanes Closed : There is one of two lanes closed.
Posted: June 22, 2018, 9:09 am
Location : The A1033 westbound. Lane Closures : Lane one will be closed. Reason : Litter clearance is planned. Status : Pending. Schedule : From 21:00 on 28 June 2018 to 06:00 on 29 June 2018. Lanes Closed : There will be one of two lanes closed.
Posted: June 22, 2018, 9:09 am
Location : The A63 eastbound between the junctions with the A1033 North and the A1033 East. Lane Closures : Lane one will be closed. Reason : Roadside drains works are planned. Status : Pending. Schedule : From 21:00 on 25 June 2018 to 06:00 on 26 June 2018. Lanes Closed : There will be one of two lanes closed.
Posted: June 22, 2018, 9:09 am
Location : The A180 eastbound entry slip from the A160 . Reason : Horticultural works are planned. Status : Pending. Schedule : Expect disruption everyday between 09:30 and 15:30 from 28 June 2018 to 29 June 2018. Lanes Closed : All lanes will be closed.
Posted: June 22, 2018, 9:09 am
Location : The A1033 eastbound. Lane Closures : Lane one will be closed. Reason : Litter clearance is planned. Status : Pending. Schedule : From 21:00 on 28 June 2018 to 06:00 on 29 June 2018. Lanes Closed : There will be one of two lanes closed.
Posted: June 22, 2018, 9:09 am
Location : The A1033 westbound. Lane Closures : Lane one will be closed. Reason : Roadside drains works are planned. Status : Pending. Schedule : From 21:00 on 27 June 2018 to 05:00 on 28 June 2018. Lanes Closed : There will be one of two lanes closed.
Posted: June 22, 2018, 9:09 am
Location : The A1033 westbound. Lane Closures : Lane one will be closed. Reason : Roadside drains works are planned. Status : Pending. Schedule : From 21:00 on 26 June 2018 to 05:00 on 27 June 2018. Lanes Closed : There will be one of two lanes closed.
Posted: June 22, 2018, 9:09 am
Location : The A63 westbound. Reason : Emergency barrier repairs are planned. Status : Pending. Schedule : Expect disruption everyday between 21:30 and 05:00 from 26 June 2018 to 28 June 2018. Lanes Closed : All lanes will be closed.
Posted: June 22, 2018, 9:09 am
Location : The A1033 eastbound. Lane Closures : Lane one will be closed. Reason : Roadside drains works are planned. Status : Pending. Schedule : From 21:00 on 26 June 2018 to 05:00 on 27 June 2018. Lanes Closed : There will be one of two lanes closed.
Posted: June 22, 2018, 9:09 am
Location : The A63 westbound between the A1079 and the junction with the A1166 . Lane Closures : Lane one will be closed. Reason : Emergency barrier repairs are planned. Status : Pending. Schedule : Expect disruption everyday between 21:30 and 05:00 from 26 June 2018 to 28 June 2018. Lanes Closed : There will be one of two lanes closed.
Posted: June 22, 2018, 9:09 am
Location : The A160 westbound between the junctions with the A1077 and the A180 . Lane Closures : Lane one will be closed. Reason : Horticultural works are planned. Status : Pending. Schedule : Expect disruption everyday between 09:30 and 15:30 from 28 June 2018 to 29 June 2018. Lanes Closed : There will be one of two lanes closed.
Posted: June 22, 2018, 9:09 am
Location : The M180 eastbound between junctions J4 and J5 . Reason : Emergency roadworks are planned. Status : Pending. Schedule : From 13:00 on 28 June 2018 to 15:00 on 28 June 2018.
Posted: June 22, 2018, 9:09 am

Announcements

Breaking News: Traffic Information

Breaking News

The latest current breaking news items for England's motorway network

The M6 in Cheshire is experiencing severe delays southbound between J19 and J18
Posted: January 1, 1970, 12:00 am

Regional Twitter feed

Keep up-to-date

Sign up for updates
Please leave feedback