M25 junction 13 improvements

Improving junction 13 of the M25 to ease congestion and manage the increasing volume of traffic on the M25.

Start date November 2019
End date November 2020
Cost £6 million

Latest updates

  • 18 December 2020

    Traffic light testing under way

    We made great progress in November and installed new technology (for example traffic control technology called MOVA), finished all resurfacing, painted new lines and completed stud work all ahead of schedule. We also put in new street lights and traffic lights.

    This month we’re testing the newly installed traffic lights. The trial will run in the background and won’t require any physical road or lane closures.

  • 13 November 2020

    Resurfacing work nears completion

    Work on the junction started in November 2019 and planned completion is scheduled for late November 2020.

    Road and lane closures are planned throughout November 2020 to enable resurfacing works, street lighting and traffic installations around the junction to take place.

    A combination of lane and full carriageway closures will be in place throughout August to enable resurfacing works around the junction to take place. Traffic management will remain in place for the duration of the closures.

    We will provide information through advanced warning signs ahead of works starting, with clearly signed diversions in place for any full closures.

    Noise barriers will be introduced to help significantly reduce noise emissions and equipment with lower noise emissions has also been identified during the design process.

    See the General information document in the Project background section below for answers to some frequently asked questions.

    If you would like to receive more information about these planned works please contact JIP@CONNECTPLUSM25.CO.UK

Project information

Overview

Improvements include changes to traffic signal control to improve traffic flow through the junction, an additional lane on the roundabout to increase capacity and an additional lane on the M25 northbound exit slip to increase capacity. This work will lead to a more free-flowing network, with reduced congestion and more reliable journey times. 

The M25 junction 13 is controlled by traffic signals, and is where the M25, A30 Staines Bypass and B376 meet. Junction 13 is operating over its design capacity, which leads to congestion, queuing traffic and journey delays during peak hours. 

These improvements will deliver safer and more reliable journeys for our customers, and manage the ever-increasing volume of traffic using the M25. 

Documents

Traffic information

Information about scheduled roadworks and events on our motorways and major roads.

Sign up for updates!

Keep up to date with what's happening on this scheme by signing up to our updates.

Feedback