Large tents appear at Trinity burial ground
Two giant tents which both stand at seven metres tall and are unmissable at 3,512 metres square and 962 metres square have been erected at Trinity Street burial ground.
Both of the tents, which have a combined length of 135 metres and are in some places as wide as 50 metres, are likely to be in place for around 12 months at the 237-year-old burial ground, which lies partially within the area of the scheme.
There are currently 25 archaeologists working on site in a safe and socially-distanced manner, and over the course of the project this will increase to a team of 85.
The careful and sensitive process of exhumation has started and is expected to take just under a year.

Pedestrian improvements to High Street underpass
We’re upgrading the pedestrian access from Market Street, and along High Street to the Fruit Market area adjacent to Queen Street. This work is necessary as we will be removing the existing A63 crossing at Market Street next year.
To carry out the work we’re installing a sheet piled wall next to the Modern Court building and the footpath nearby, parallel to the A63. The work will be carried out overnight on Friday 13 and Saturday 14 November so it will be outside of the courts working hours which is nearby.
This work is likely to cause some noise, however we’ll do everything we can to minimise that disturbance.
Old Town improvements get under way
Work starts this week on closing the access on to the A63 from Vicar Lane, Fish Street and Dagger Lane. We’ll be providing a turning head on each of these streets to enable traffic to turn around. They will be constructed using cobbles to ensure they match the existing surfacing to maintain the feel of the conservation area.
As part of this work South Churchside will also become a two way road. We won’t be altering the surfacing but there will be a small loss of on-street parking, however there won’t be any changes to the disabled parking.

The work will be carried out between 7.30am and 6pm weekdays and 8am until 1pm on Saturdays.
Details of the closures
Work will start on South Church Side and Robinson Row on Friday 23 October for a week. This will create a two way street from Market Place to Robinson Row and the priority at the junction of Fish Street/South Church Side will be changed.
From Monday 26 October access from the A63 to Grammar School Yard will be closed. We’ll create the new access first and work is expected to take around six weeks.
From Monday 2 November we’ll be closing access on to the A63 from Vicar Lane. A new turning head will be created and pedestrian access will not be affected. This is expected to take around four weeks.
In the new year work will start on closing off access from Fish Street. A new turning head will be created and work will start on Monday 4 January. It is expected to take around four weeks.
We’ll be created two way access between Dagger Lane and Princes Dock Street on Posterngate from Friday 8 January for around a week.
On Wednesday 4 January for four weeks we’ll be closing access from Dagger Lane. It will become two way from Robinson Row to the A63 and the two way will remain from Robinson Row to Posterngate.
Princes Dock Street will become one way from the A63 junction from Monday 1 March. The work is expected to take around a week to complete.
Whitefrairgate/Parliament Street and North Church Side/Trinity House lane will remain unaffected.
Specialist equipment arrives at Arco
As you’ll be aware the nature of the ground in Hull is rather soft in places due to the soil deposits along the flood banks of the River Humber. The scheme requires a complex engineering solution in order to construct the underpass which will eventually replace the existing junction at Mytongate.
This solution includes the installation of underground walls either side of the underpass known as diaphragm walls, concrete foundations to help us stabilise the ground and prevent any water getting into the underpass and treatment of the existing poor ground.
In order to prepare for this part of work, which won’t start until next year, some work to perfect the solution is taking place in the southern car park of the Arco site at Waverley Street. This site has been selected as the ground conditions are very similar to those in which the final work will take place in the centre of the underpass.
Arco have been kind enough to allow our contractor Balfour Beatty to use the car park as the trial area to determine how these solutions perform in this ground.
To carry this out several specialist pieces of equipment including a drilling rig and large crane style excavator are being delivered to the site. This work started in September and will last until the end of January 2021. Work will be limited to daytime hours and we’ll monitor noise and vibration caused by the work to ensure it is kept to a minimum.
