M56 maintenance schemes

Project information

View a project

The following projects are part of the M56 maintenance programme:

From: March 2020   To: November 2020

We’re pleased to confirm our work on the M56 at Helsby Viaduct is now complete. We managed to complete the following improvements four months ahead of schedule:

  • Installed new drainage systems
  • waterproofed the bridge deck and replacing bridge joints
  • installed new safety barrier at the sides and within the central reservation
  • resurfaced the carriageway and replacement of road markings

All narrow lanes have been removed and all lanes have reopened to traffic.

Concrete repairs will continue underneath the viaduct; however this will cause no disruption to the road user.

From: 10 August 2020   To: 31 August 2020

Work to replace the road markings on the M56 between junctions 9 and 10 is shortly due to start. This will take place on both sides of the carriageway and will include the replacement of road studs. Our aim is to ensure we keep the network safe and operational, as well as improving journeys for our customers.

Work is due to start on or shortly after 10 August 2020 for approximately three weeks. This will take place Monday to Friday, between the hours of 9pm and 5am.

For safety purposes, overnight lane closures are required on the M56 between junctions 9 and 10. Associated link road closures at junctions 9 and 10 are also required, and localised signed diversion routes will be in place.

From: 13 July 2020    To: End of August 2020

Following the completion of our survey work, we have a full understanding of what repairs are needed to the drainage system underneath the M56 between junctions 6 and 8. We’re now due to carry out work to repair the drainage within the central reservation. Our aim is to ensure we keep the network safe and operational, as well as improving journeys for our customers.

Advance work will start from 13 July 2020 for approximately one week. The main drainage repairs will follow for a further seven weeks. These works will take place Monday to Friday, between the hours of 9pm and 5am.

For safety purposes, temporary narrow lanes and a reduced speed limit of 50mph will be in place on both sides of the carriageway. In addition to this, overnight full closures are also required to safely install and remove the narrow lanes. The full closures will be in place from 9pm to 4am on the following dates:

  • M56 between junctions 6 and 8 westbound - 21/22 August
  • M56 between junctions 7 and 6 eastbound - 5 and 22/23 August

M56 junctions 6 to 8 smart motorway project

Shortly after the drainage repair work is fully complete, the main construction work for the M56 junctions 6 to 8 smart motorway project will start. Further communication will be provided closer to the time.

Diversions

Closure of M56 westbound between junctions 6 and 8 Closure of M56 eastbound between junctions 8 and 6

Documents

Traffic information

Information about scheduled roadworks and events on our motorways and major roads.

Sign up for updates!

Keep up to date with what's happening on this scheme by signing up to our updates.