A57 Link Roads

We're investigating ways to improve connectivity between Manchester and Sheffield.

Start date January - March 2023
End date Road Period 3 (2025 - 2030)
Cost TBC

Latest updates

  • 05 November 2020

    Consultation now open – 5 November to 17 December 2020

    We’ve launched a consultation on the A57 Link Roads project and we want to hear your views on the updated design of the proposed road. The consultation is open until 23:59 on 17 December 2020.

    Following questions raised at our 2018 consultation, we’ve also revisited our air quality data and other environmental impacts. We’ve carried out additional monitoring and assessments, and we now have more environmental information available for you to view.  

    You can find all of our consultation materials and respond to the consultation by visiting our consultation page.

    Our traffic data is still being finalised and is therefore not yet available to view. We will be publishing this data when we make our application for a Development Consent Order in 2021. This follows the normal process for developing a ‘Nationally Significant Infrastructure Project’. You can register as an interested party during the ‘Development Consent Order’ process, to have the opportunity to share your views on this data with the Planning Inspectorate.

    Due to COVID-19 restrictions, we’re not holding face-to-face events as we normally would. Instead, we’re providing a range of alternative ways for you to speak to the project team, ask questions and ultimately make an informed response to the public consultation.

    If you have any questions about the consultation or the project, you can join one of our telephone consultation events by calling our freephone number 0808 196 4502 during the dates and times below:

    • Tuesday 10 November - 10am to 3pm and 4pm to 8pm
    • Tuesday 17 November - 10am to 3pm and 4pm to 8pm
    • Tuesday 24 November - 10am to 3pm and 4pm to 8pm

    If you have any technical questions which we’re unable to answer on the phone, we will arrange for a member from one of our technical teams to call you back. This will be on the following Thursday, at a time convenient for you.

    You can also join one of our webinars where we’ll present our proposals and hold a question and answer session. These will be held on the following dates and times:

    Please note: you may need to download the Microsoft Teams application onto your device to join these webinars.

    If you’re unable to access any of our materials or require these in a different format, please contact us on 0300 123 5000.

    You can watch this short video which explains the “Development Consent Order” process which we must follow to obtain consent to build the scheme. 

  • 29 October 2020

    Upcoming consultation

    We’re preparing to launch a public consultation from 5 November to 17 December 2020 on the changes that we’ve made to the design of the project since our last consultation in 2018. We’ve also carried out additional environmental surveys and monitoring, and we want to hear your views on the most recent data, and our plans for reducing the environmental impacts of the project.

    When the consultation launches, we will upload all of our consultation materials on this web page, including an online response form.

    We have published our ‘Statement of Community Consultation’ which sets out how we will carry out this consultation. You can view this in the documents section of this webpage.

    You can sign up to be notified via email when we update this page.

  • 25 August 2020

    Change to scheme delivery dates

    During 2018 we consulted with stakeholders and the public on our proposed plans for the Trans-Pennine upgrade project. Since then, we've been carrying out further air quality monitoring alongside our ongoing air quality assessment to ensure the scheme doesn’t affect areas of pre-existing air quality exceedances.

    It's important this data is in place before presenting our findings to all interested parties.

    The gathering and analysis of the air quality monitoring data has had an impact on the timescales for the delivery of the link roads, meaning that we now intend to start construction work on this project in early 2023. We plan to hold another consultation on the latest design and environmental information for the project later this year. Keep an eye on our web page for more details about the consultation, or sign up for email alerts when we update this web page with the latest information.

Project information

Overview

The A57 Link Roads project was formerly known as the “Trans-Pennine Upgrade”, and is referred to as the “Mottram Moor Link Road and A57 Link Road project” in the Government’s second Roads Investment Strategy.

The A57 and A628 between Manchester and Sheffield currently suffer from heavy congestion, creating unreliable journeys. This restricts potential economic growth, as the delivery of goods to businesses is often delayed and the route is not ideal for commuters, which limits employment opportunities. 

Much of this heavy traffic travels through local roads, which disrupts the lives of communities and makes it difficult and potentially unsafe for pedestrians to cross the roads. These issues will only get worse with time if significant improvements aren’t made.

The current scheme has evolved over more than 50 years as different ideas have been explored. In 2017, after a wide consultation about a number of different options, we announced a package of Trans-Pennine Upgrade work, to improve the existing route connecting the M67 at Mottram in Longdendale to the M1, north of Sheffield.

We held another consultation on the proposed package of upgrades in 2018, and have since split the work into two projects which are being delivered separately:

  • Upgrades to the Westwood roundabout near Sheffield; packaged with technology improvements along the A628, A616 and A61, including electronic signs and improved closure gates
  • Creation of two new link roads at the western end of the A57/A628 route, to provide a dual carriageway bypass around Mottram in Longdendale

The A57 Link Roads project will include the creation of two new link roads:

  • Mottram Moor Link Road – a new dual carriageway from the M67 junction 4 roundabout to a new junction on the A57(T) at Mottram Moor
  • A57 Link Road – a new single carriageway link from the A57(T) at Mottram Moor to a new junction on the A57 in Woolley Bridge.

We started construction on the Westwood roundabout and technology improvements in March 2020. However, as the A57 Link Roads scheme is classed as a ‘Nationally Significant Infrastructure Project’, to build it, we need to apply for a ‘Development Consent Order (DCO)’, which will be examined by the Planning Inspectorate and approved by the Secretary of State.

Our DCO video explains more about this process.

The scheme will:

  • Reduce congestion and improve the reliability of people’s journeys - through Mottram in Longdendale and between Manchester and Sheffield
  • Reduce noise levels and pollution for neighbouring properties - by reducing the amount of traffic from the existing A57 through Mottram in Longdendale
  • Re-connect local communities and create better conditions for pedestrians, cyclists and equestrians - in Mottram in Longdendale
  • Reduce delays and queues that impact the community - affecting residents, businesses and public transport in the area

Documents

Traffic information

Information about scheduled roadworks and events on our motorways and major roads.

Sign up for updates!

Keep up to date with what's happening on this scheme by signing up to our updates.

Feedback